00225.05 Contractor's Traffic Control Plan. <br />(DELETE) The first sentence. <br />(ADD) The Traffic Control Plan in the plan set has been approved, by the Engineer, for <br />use by the Contractor. It is the Contractor's responsibility to modify this TCP as <br />necessary to provide a complete TCP for the Contractor's Work operations. Any <br />modifications to this plan requires that the Contractor shall submit a detailed <br />Work schedule showing stage construction along with the Traffic Control Plan(s) <br />(TCP) in writing five (5) Work Days before the pre-construction conference for <br />approval. If, as determined by the Engineer, the TCP does not meet these <br />requirements the TCP will be rejected and no adjustment of. Contract Time will be <br />allowed.. <br />00225.11 Temporary Signing <br />(b) Sign Supports <br />(ADD) (6) City Provided Special Information Signs <br />City Provided Special Information Signs shall be post mounted in accordance <br />with OREGON Standard Drawing TM 100. <br />00225.41 Temporary Signing <br />(ADD) (h) City Provided and Special Signs <br />Install PCMS and City Provided Special Information Signs five (5) Work days <br />prior to commencement of any other Contract Work, with, the exception of <br />placement of erosion control. - <br />00225.43 Temporary Traffic Delineation <br />(g) Striping <br />(ADD) Temporary striping shall include all existing pavement striping and markings, <br />excluding bike lane stripes, bike markings, and delineation of parking spaces. <br />(1) Base Courses <br />(ADD) For cold plane surfaces, temporary striping shall be painted, use of reflective <br />flexible overlay pavement markers will not be allowed. <br />00225.90A Method 1111 Lump Sum Basis - <br />(DELETE) Entire paragraph. <br />(ADD) Payment for the item "Temporary Work Zone Traffic Control, Complete" will be <br />made at the Contract lump sum amount and will be for furnishing, installing, <br />moving, operating, maintaining, inspecting, and removing materials and TCD <br />(excluding temporary striping and City Provided Special Information signs), and <br />for furnishing all equipment, labor, and incidentals necessary to complete the <br />Work as specified. <br />Special Provisions Job #'s 4583, 4617 and 4655 Page 5 <br />