New Search
My WebLink
|
Help
|
About
|
Sign Out
New Search
2003-07 EWEB CIP Draft
COE
>
PW
>
Admin
>
Execs
>
Executive non-confidential
>
Historical
>
2003-07 EWEB CIP Draft
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
6/8/2009 12:30:48 PM
Creation date
6/1/2009 12:30:45 PM
Metadata
Fields
Template:
PW_Exec
PW_Division_Exec
Administration
PWA_Project_Area
Miscellaneous
PW_Subject
EWEB CIP
Document_Date
9/30/2002
External_View
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
35
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
Show annotations
View images
View plain text
Land Acquisition Not Included SDC Funded $320,000 <br />Engineering & Inspection $ 80,000 Rate Funded Capital $320,000 <br />EWEB Labor $ 20,000 <br />Construction $700,000 <br />Administration 40 000 <br />Total Cost $840,000 <br />Willamette 1325 Reservoir <br />Currently, the Willamette 1325 system is served by a temporary 50,000 gallon bolt-up steel reservoir that will <br />be replaced by a 200-300,000 gallon permanent reservoir sometime later in the decade. This reservoir will <br />eventually serve most of the 1325 system in the Willamette, Hillcrest and College Crest systems. There needs <br />to be further analysis of build out demands in [his area, versus existing demands. For now, assume a 50 percent <br />eligibility for SDC funding. <br />Land Acquisition Already Own Land SDC Funded $326,500 <br />Engineering $ 90,000 Rate Funded Capital $326,500 <br />EWEB Labor $ 20,000 <br />Piping & Construction $500,000 <br />Administration 43 000 <br />Total Cost $653,000 <br />Timberline 800 Reservoir -Design & Construction <br />The College Crest 800, College Hill 703, City View 800, and Timberline 800 service areas will be <br />interconnected in the future. Build out population for this azea will require an additional 500,000 gallon <br />reservoir. The reservoir will be constructed on a site yet to be purchased near Timberline Drive. <br />Land Acquisition Not included SDC Funded $338,800 <br />Engineering & Inspection $ 60,000 Rate Funded Capital $266,200 <br />EWEB Labor $ 15,000 <br />Construction $500,000 <br />Administration 30 000 <br />Total Cost $605,000 <br />Reservoir Improvements <br />City View/Crest 975 Prestressed Reservoir Repair <br />EWEB has completed repairs of six out of eight prestressed concrete reservoirs`constructed in the 1960's. Poor <br />construction methods resulted in separation of the exterior grout from the prestressed wire bands, weakening the <br />structural integrity and life of the reservoirs. EWEB estimates that by conducting these repairs we aze adding <br />twenty-five to thirty-five yeazs of life on these structures. The remaining two reservoirs that need-to be <br />refurbished are the City View 975 and the Crept 975 reservoirs. From reconnaissance conducted on these <br />reservoirs, EWEB anticipates that these reservoirs will need the least repair work. These reservoirs will be <br />repaired within the same year. _ <br />Engineering $ 15,000 SDC Funded $ 0 <br />Repairs & Construction $112,000 Rate Funded Capital $135,000 <br />Administration 8000 <br />Total Cost $135,000: <br />
The URL can be used to link to this page
Your browser does not support the video tag.