Stormwater <br />Pine View Neighborhood Facility Construct a 4 ac-ft neighborhood water quality facility upstream of the Pine View <br />development outfall. <br />Plan/Policy Document: CSWMP; Stormwater Basin Plans <br />Total Project Cost: $309,000 <br />Polk Street Water Quality Facilities Construct off-line, underground water quality facilities for this existing piped <br />drainage system. Funds previously budgeted for preliminary design. Final design <br />and construction in FY02. <br />Plan/Policy Document: CSWMP, Stormwater Basin Plans <br />Total Project Cost: $207,000 <br />River Point Pond Outlet Channel Construct an open waterway drainage system from River Point Pond to the McKenzie <br />River. Funds previously budgeted for preliminary design. Design delayed due to <br />environmental issues. Final design and construction FY03. <br />Plan/Policy Document Stormwater Basin Plans <br />Total Project Cost $275,000 <br />Royal Node Stormwater Infrastructure Enhance existing open waterways to achieve multiple benefits including <br />conveyance, waterqualiry, and natural enhancements. <br />Plan/Policy Document: CSWMP; Stormwater Basin Plans, Royal Node Plan <br />Total Project Cost $1,399,000 <br />Water Quality Facilities -High Source Areas Construct offline, underground structural water quality facilities in developed, high <br />pollutant source areas. <br />Plan/Policy Document CSWMP; Stormwater Basin Plans <br />Total Project Cost $900,000 <br />Stormwater Rehabilitation/Imarovements <br />Ayres Pond Outfall Retrofit Install a Stormwater quality structure (CDS) upstream of the outfall to Ayres Pond to <br />remove large debris from the inaccessible lower portions of the open channel. <br />Retrofit the existing outfall structure with a larger concrete pad and energy dissipaters. <br />Plan/Policy Document CSWMP; Stormwater Basin Plans <br />Total Project Cost $774,000 <br />City of Eugene 2002-2007 Capital Improvement Program <br />53 <br />