. <br />. ~ <br />UO Arena Mitigation, City Priorities, <br />5- Franklin Blvd. and Orchard <br /> 7/29I2008 , <br /> Construction Costs Quantitv Unit Unit Price Extended Total <br />0010 Mobilization 1 LS 15% of const $2,900.63 : <br />0020 Temporary Work Zone Traffic Control - Complete 1 LS $1,500.00 $1,500.00 <br />0030 Erosion Control 1 LS $500.00 $500.00 <br />0040 Sawcufting 525 LF $1.50 $787.50 <br />0050 Excavation -200 CY $25.00 $5,000.00 <br />0060 Concrete Walk, 4" 360 SF $4:50 $1,620.00 <br />0070 Concrete Driveway, 7" 300 SF $8.00 $2,400.00 <br />0080 Concrete Curb and Gutter .' 150 LF $25.00 $3,750.00 <br />0090 Landscaping 1 LS $3,500.00 $3,500.00 <br />0100 Striping, Parking Spaces (white paint) 80 LF $3:50' $280.00 <br />0110 Remove and relocate bus shelter complete 1 LS $8,000.00 $8,000.00 <br /> Totai Construction ` <br />~ $30,238.13 <br />' <br /> Testing (percent of construction) 2% $604.76 <br /> Contingency (percent of construction) 25% $7,559.53 <br /> Engineering (percent of construction, testing, contingency) 20%0 $7,680.48 <br /> Total $46,082.90 <br />' Estimated Total . $46,000 <br />