CIP Policy Issues <br /> Stormwater -Delta Ponds <br /> The Delta Ponds project is a Corps of Engineers restoration project under Section 206 of <br /> the Water Resources Development Act with a recreation component.. The restoration <br /> component of the project is cost-shared 65-35 between the Corps and the City, <br /> respectively. The recreation component is cost-shared 50-50 between the Corps and the <br /> City up to 10 percent of the cost of the Corps share of the restoration component. <br /> Recreation costs beyond 10 percent of the cost of the Corps share of the restoration <br /> component are 100 percent City costs. The following table outlines the allocation of the <br /> estimated project cost of $6,215,100: <br /> City Co s Total <br /> Restoration $1,901,480 $3,531,320 $5,432,800 <br /> Recreation $429,168 $353,132 $782,300 <br /> Total $2,330,648 3,884,452 $6,215,100 <br /> The City's FY 03 budget included funds for the Delta Ponds project and the City is being <br /> credited the value of the lands as part of its share of the total project costs. The following <br /> table outlines the City's appropriated (FY 03) and unappropriated (CIP) shares of the <br /> project: <br /> FY 03 CIP Total <br /> Lands $878,000 $0 $878,000 <br /> Recreation (Parks SDC or Bond $200,000 $250,000 $450,000 <br /> Restoration Stormwater *$800,000 $400,000 $1,200,000 <br /> Total $1,878,000 $650,000 $2,528,000 <br /> * There is $644,000 remaining of the funds budgeted. <br /> There are also components of the Delta Ponds plan that are outside of the Corps project. <br /> There is an opportunity to extend the East Bank bike path under Goodpasture Road and <br /> Delta Highway and connect the bike path to the neighborhood to the east..The additional <br /> "dry" culverts under Goodpasture Road and Delta Highway could be constructed with the <br /> Corps project at 100 percent City cost. Constructing the culverts as part of the Corps <br /> <br /> project would cost approximately $700,000. In addition, the County will allow an open <br /> cut of Delta Highway as part of the Corps project in advance of their scheduled overlay <br /> project. The 900-foot long by 10-foot wide concrete bike path with illumination could be <br /> completed by the City at City cost upon completion of the Corps project. The estimated <br /> cost of the bike path is $120,000. <br /> There is an opportunity to complete the loop of the soft recreational pathway around the <br /> western edge of the Delta Ponds between Goodpasture Road and Delta Highway. The <br /> 2,400-foot long by six-foot wide gravel path could be completed by the City at City cost <br /> upon the completion of the Corps project. The estimated cost is $12,000. <br /> <br />