00225.90A Method "B"- Lump Sum Basis - <br /> (DELETE) Entire paragraph. <br /> (ApD) .Payment for the item "Temporary Work Zone Traffic Control, Complete" will be <br /> made at the Contract Lump Sum amount and wil! be for furnishing, ins#alling, <br /> moving, operating, maintaining, inspecting, and removing materials and TCD - <br /> (excluding temporary striping), and for furnishing ail equipment, labor, and <br /> incidentals necessary to complete the work as specified. Flagging is incidental to <br /> °Temporary Work Zone Traffic Control, Complete". <br /> Revisions to the provided TCP necessary to accommodate the Contractor's <br /> operations or traffic conditions shall b® incidental. <br /> Ob225.93 , .Temporary Traffic Delineation - <br /> (ADD) Temporary marking of crosswalks and stop bars will be paid for as "Temporary <br /> Striping". ~ ~ <br /> 80280.00 General - <br /> ~ADD) Construct inlet protection prior to any other work with the project limits and <br /> perform all work in accordance with Section 00280 °Erosion and Sediment. <br /> Control". t _ <br /> 00641.91 Material on Hand - <br /> (DELETE) Entire Section. <br /> 00706.12 Aggregate <br /> (ADD) Sand Equivalency (SE) shall be between 45 and 55. <br /> 00706.12(a) Aggregate ~ ~ ~ <br /> (ADD) Aggregate gradation shall be Type tt. <br /> (ADD) 00706.18 Crack seas, Sealant <br /> Sealant.,material shall comply with section 00746.10 <br /> 00706.41 Preparation of Surface <br /> (ADD) HMAC surface repairs and crack sealing shall be completed no less than 14 <br /> calendar days prior to slurry seal application. <br /> 00706.41(b) Surface Repairs <br /> r <br /> (ADD) Level 2,'/" dense graded HMAC shall be Osed for surface repairs where shown <br /> the construction plans or diree#ed by the engineer. <br /> <br /> J Specie{ Provisions -Job #4510 Page 3 <br /> <br />