<br /> " Page 8 of 10 ' <br /> C HANG ~ O R D T R <br /> aildiah Job # 3237 <br /> City of Eugene Job # 4183 <br /> CHANGE ORDER: EV-04 <br /> PROJECT: Airpozt Runway <br /> Elect Vault Bldq <br /> The following changes are proposed: <br /> Reference Owner/Proj. Change Order 2 <br /> The revised drawing V13 thickens the floor slab to a <br /> section of the regulator room to S" thick with #4 <br /> • rebar at 9" on center. <br /> Labor and N~terials: $ 4 6.67 <br /> Total Add/(Deduct) Costs This Change Order: 546.67 <br /> Total Above ~ ~ 546.67 <br /> Overhead & Profit (15~) 57.00 <br /> Proposed Change Order Cost_ 553.67 <br /> Recommended by ~,,,;.,..'~e~.~•---- <br /> Tim Bonn, Project Engineer Date : 9/,~Aib y <br /> 8 <br /> <br />