<br /> ' ~ Page6of10 <br /> CHANGE ORDJ~R <br /> Wildiah Job # 3237 <br /> City of Eugene Job # 4183 <br /> CHANGE ORDER: EV-02 <br /> PROJECT: Airport Runway <br /> Elect Vault Hldg <br /> The following changes are proposed: <br /> Reference Owner/Proj. Change Order Field regt by Mead & Hunt <br /> During field walk, Mead & Hunt directed the <br /> relocation of electrical meters and CT cans to the <br /> East wall, and to smooth block to that section of <br /> wall. <br /> Paddock Masonry: $ 3 8 8.61 <br /> Total Add/(Deduct> Costs This Change Order: 5388.61 <br /> Total Above $388.61 <br /> Overhead & Profit (15~? $58.29 <br /> Proposed Change Order Cost ~ $446.90 <br /> Recommended by <br /> Tim Bonn, Project Engineer Date : 9/2p/oy <br /> 6 <br /> <br />