<br /> EUGENE SCHOOL DISTRICT 4J - MULTI -USE ATHLETIC FIELDS STUDY
<br /> PROJECT COST SUMMARY FEBRUARY 4, 1999
<br /> OPTION 2 - SINGLE FIELD
<br /> KENNEDY MIDDLE SCHOOL / CHURCHILL HIGH SCHOOL c TRACK
<br /> A B C D E F
<br /> BASIC BASIC FIELD ADD ADD ADD ALL
<br /> FIELD & UTILITY BLEACHERS ADDITIONAL RESTROOMS & FEATURES
<br /> COSTS SERVICES & LIGHTS COMPONENTS CONCESSIONS INCLUDED
<br /> BASIC FIELD COMPONENTS
<br /> 1 FIELD ENGINEERING $12,814 $12,814 512,814 $12,814 $12,814 $12,814
<br /> 2 FIELD SURFACE AND DRAINAGE $951,440 $951,440 $951,440 $951,440 $951,440 $951,440
<br /> 3 CHAIN LINK FENCE AND GATES $37,148 $37,148 537,148 $37,148 $37,148 537,148
<br /> 4 PAVEMENT BETWEEN FENCE AND FIELD $180,984 $180,984 $180,984 $180,984 $180,984 5180,984
<br /> 5 WALKWAY BETWEEN PARKING AND FIELD $75,133 $75,133 $75,133 $75,133 $75,133 $75,133
<br /> 6 EMERGENCY AND SERVICE VEHICLE ACCESS $0 $0 $0 $0 $0 $0
<br /> 7 TRACK AND FIELD AMENITIES REPLACEMENT $36,520 $36,520 $36,520 $36,520 $36,520 $36,520
<br /> 8 GOAL POSTS $5,638 $5,638 $5,638 $5,638 $5,638 $5,638
<br /> SUB -TOTAL BASIC FIELD COMPONENTS $1,299,677
<br /> BASIC UTILITY SERVICES ROUGH -IN
<br /> 9 ADD FIRE WATER UTILITY SERVICE $53,892 $53,892 $53,892 $53,892 $53,892
<br /> 10 ADD ELECTRICAL UTILITY SERVICE $43,978 $43,978 $43,978 $43,978 $43,978
<br /> SUB -TOTAL BASIC FIELD COMPONENTS & UTILITY ROUGH -IN $1,397,547
<br /> ADDITIONAL PROJECT ENHANCEMENTS
<br /> ADD BLEACHERS AND FIELD LIGHTING
<br /> 11 ADD 2000 SEAT GRANDSTAND $593,018 $593,018 $593,018 $593,018
<br /> 12 ADD ELEVATOR TO OBSERVATION BOOTH $0 $0 $0 $0
<br /> 13 ADD FIELD LIGHTING $132,460 $132,460 5132,460 $132,460
<br /> I SUB -TOTAL BASIC FIELD COMP. & UTILITY ROUGH -IN & BLEACHERS & LIGHTING $2,123,025
<br /> ADD OTHER PROPOSED PROJECT AMENITIES
<br /> 14 ADD SCORE BOARD $23,312 $23,312 523,312
<br /> 15 ADD ACOUSTICAL SOUND SYSTEM $18,794 $18,794 518,794
<br /> 16 ADD DUMPSTER STORAGE AREA $6,172 $6,172 $6,172
<br /> I ADD ADDITIONAL COMPONENTS 52,171,303
<br /> ADD REST ROOM FACILITIES
<br /> 17 ADD RESTROOM FACILITIES $339,967 5339,967
<br /> 18 ADD CONCESSION BUILDING 572,899 $72,899
<br /> 19 ADD SANITARY SEWER UTILITY SERVICE $49,070 549,070
<br /> 20 ADD DOMESTIC WATER UTILITY SERVICE $47,033 $47,033
<br /> I SUB -TOTAL FIELDS & UTILITY ROUGH -IN & BLEACHERS & LIGHTING & RESTROOMS 52,680,272
<br /> REMAINING PROJECT COMPONENTS
<br /> 21 ADD WALKWAY LIGHTING BETWEEN PARKING AND FIELD 5106,936
<br /> 22 ADD TEAM SUPPORT FACILITIES $410,952
<br /> I TOTAL PROJECT COSTS FOR ALL PROJECT COMPONENTS $3,198,160