EUGENE SCHOOL DISTRICT 4J - MULTI -USE ATHLETIC FIELDS STUDY
<br /> PROJECT COST SUMMARY FEBRUARY 4, 1999
<br /> OPTION 2 - SINGLE FIELD
<br /> KENNEDY MIDDLE SCHOOL / CHURCHILL HIGH SCHOOL @ SOUTH OF TRACK
<br /> A B C D E F
<br /> BASIC BASIC FIELD ADD ADD ADD ALL
<br /> FIELD & UTILITY BLEACHERS ADDITIONAL RESTROOMS & FEATURES
<br /> COSTS SERVICES & LIGHTS COMPONENTS CONCESSIONS INCLUDED
<br /> BASIC FIELD COMPONENTS
<br /> 1 FIELD ENGINEERING $12,012 $12,012 $12,012 $12,012 $12,012 $12,012
<br /> 2 FIELD SURFACE AND DRAINAGE $947,998 $947,998 $947,998 $947,998 $947,998 $947,998
<br /> 3 CHAIN LINK FENCE AND GATES $31,171 $31,171 $31,171 $31,171 $31,171 $31,171
<br /> 4 PAVEMENT BETWEEN FENCE AND FIELD $143,919 $143,919 $143,919 $143,919 $143,919 $143,919
<br /> 5 WALKWAY BETWEEN PARKING AND FIELD $31,055 $31,055 $31,055 $31,055 $31,055 $31,055
<br /> 6 EMERGENCY AND SERVICE VEHICLE ACCESS $70,483 $70,483 $70,483 $70,483 $70,483 $70,483
<br /> 7 TRACK AND FIELD AMENITIES REPLACEMENT $0 $0 $0 $0 $0 $0
<br /> 8 GOAL POSTS $5,638 $5,638 $5,638 $5,638 $5,638 $5,638
<br /> I SUB -TOTAL BASIC FIELD COMPONENTS 51,242,276
<br /> BASIC UTILITY SERVICES ROUGH -IN
<br /> 9 ADD FIRE WATER UTILITY SERVICE $23,764 $23,764 $23,764 $23,764 $23,764
<br /> 10 ADD ELECTRICAL UTILITY SERVICE $44,904 $44,904 $44,904 $44,904 $44,904
<br /> SUB -TOTAL BASIC FIELD COMPONENTS & UTILITY ROUGH -IN 51,310,944
<br /> ADDITIONAL PROJECT ENHANCEMENTS
<br /> ADD BLEACHERS AND FIELD LIGHTING
<br /> 11 ADD 2000 SEAT GRANDSTAND $593,018 $593,018 $593,018 $593,018
<br /> 12 ADD ELEVATOR TO OBSERVATION BOOTH $0 $0 $0 $0
<br /> 13 ADD FIELD LIGHTING $127,535 $127,535 $127,535 $127,535
<br /> I SUB -TOTAL BASIC FIELD COMP. & UTILITY ROUGH -IN & BLEACHERS & LIGHTING 52,031,497
<br /> ADD OTHER PROPOSED PROJECT AMENITIES
<br /> 14 ADD SCORE BOARD $23,312 $23,312 $23,312
<br /> 15 ADD ACOUSTICAL SOUND SYSTEM $18,794 $18,794 $18,794
<br /> 16 ADD DUMPSTER STORAGE AREA $6,172 $6,172 $6,172
<br /> I ADD ADDITIONAL COMPONENTS $2,079,775
<br /> ADD REST ROOM FACILITIES
<br /> 17 ADD RESTROOM FACILITIES $339,967 $339,967
<br /> 18 ADD CONCESSION BUILDING $72,899 $72,899
<br /> 19 ADD SANITARY SEWER UTILITY SERVICE $71,059 $71,059
<br /> 20 ADD DOMESTIC WATER UTILITY SERVICE $62,194 $62,194
<br /> I SUB -TOTAL FIELDS & UTILITY ROUGH4N & BLEACHERS & LIGHTING & RESTROOMS $2,625,894
<br /> REMAINING PROJECT COMPONENTS
<br /> 21 ADD WALKWAY LIGHTING BETWEEN PARKING AND FIELD $79,083
<br /> 22 ADD TEAM SUPPORT FACILITIES $410,952
<br /> I TOTAL PROJECT COSTS FOR ALL PROJECT COMPONENTS $3,115,929
<br /> •
<br /> WBGS ARCHITECTURE PLANNING PC 2/4199
<br /> PROJECT COST SUMMARY PAGE 7