EUGENE SCHOOL DISTRICT 4J - MULTI -USE ATHLETIC FIELDS STUDY
<br /> PROJECT COST SUMMARY FEBRUARY 4, 1999
<br /> OPTION 1 - FOUR SEPARATE FIELDS
<br /> SHELDON HIGH SCHOOL -ON EXISTING FIELDS EAST OF TRACK
<br /> A B C D E F
<br /> BASIC BASIC FIELD ADD ADD ADD ALL
<br /> FIELD & UTILITY BLEACHERS ADDITIONAL RESTROOMS & FEATURES
<br /> COSTS SERVICES & LIGHTS COMPONENTS CONCESSIONS INCLUDED
<br /> BASIC FIELD COMPONENTS
<br /> 1 FIELD ENGINEERING $8,486 $8,486 $8,486 $8,486 $8,486 $8,486
<br /> 2 FIELD SURFACE AND DRAINAGE $955,019 $955,019 $955,019 $955,019 $955,019 $955,019
<br /> 3 CHAIN LINK FENCE AND GATES $26,740 $26,740 $26,740 $26,740 $26,740 $26,740
<br /> 4 PAVEMENT BETWEEN FENCE AND FIELD $133,221 $133,221 $133,221 $133,221 $133,221 $133,221
<br /> 5 WALKWAY BETWEEN PARKING AND FIELD $22,540 $22,540 $22,540 $22,540 $22,540 $22,540
<br /> 6 EMERGENCY AND SERVICE VEHICLE ACCESS $0 $0 $0 $0 $0 $0
<br /> 7 TRACK AND FIELD AMENITIES REPLACEMENT $16,499 $16,499 $16,499 $16,499 $16,499 $16,499
<br /> 8 GOAL POSTS $5,638 $5,638 $5,638 $5,638 $5,638 $5,638
<br /> SUB -TOTAL BASIC FIELD COMPONENTS $1,168,143
<br /> BASIC UTILITY SERVICES ROUGH -IN
<br /> 9 ADD FIRE WATER UTILITY SERVICE $13,116 $13,116 $13,116 $13,116 $13,116
<br /> 10 ADD ELECTRICAL UTILITY SERVICE $45,830 $45,830 $45,830 $45,830 $45,830
<br /> I SUB -TOTAL BASIC FIELD COMPONENTS & UTILITY ROUGH -IN $1,227,089
<br /> ADDITIONAL PROJECT ENHANCEMENTS
<br /> ADD BLEACHERS AND FIELD LIGHTING
<br /> 11 ADD 1000 SEAT GRANDSTAND $194,703 $194,703 $194,703 $194,703
<br /> 12 ADD ELEVATOR TO OBSERVATION BOOTH $0 $0 $0 $0
<br /> 13 ADD FIELD LIGHTING $127,535 $127,535 $127,535 $127,535
<br /> I SUB -TOTAL BASIC FIELD COMP. & UTILITY ROUGH -IN & BLEACHERS & LIGHTING $1,549,327
<br /> ADD OTHER PROPOSED PROJECT AMENITIES
<br /> 14 ADD SCORE BOARD $23,312 $23,312 $23,312
<br /> 15 ADD ACOUSTICAL SOUND SYSTEM $18,794 $18,794 $18,794
<br /> 16 ADD DUMPSTER STORAGE AREA $6,172 $6,172 $6,172
<br /> ADD ADDITIONAL COMPONENTS $1,597,605
<br /> ADD REST ROOM FACILITIES
<br /> 17 ADD RESTROOM FACILITIES $278,154 $278,154
<br /> 18 ADD CONCESSION BUILDING $72,899 $72,899
<br /> 19 ADD SANITARY SEWER UTILITY SERVICE $31,710 $31,710
<br /> 20 ADD DOMESTIC WATER UTILITY SERVICE $7,098 $7,098
<br /> I SUB -TOTAL FIELDS & UTILITY ROUGH4N & BLEACHERS & LIGHTING & RESTROOMS $1,987,466
<br /> REMAINING PROJECT COMPONENTS
<br /> 21 ADD WALKWAY LIGHTING BETWEEN PARKING AND FIELD $114,497
<br /> I TOTAL PROJECT COSTS FOR ALL PROJECT COMPONENTS $2,101,963
<br /> WBGS ARCHITECTURE PLANNING PC 2/4/99
<br /> PROJECT COST SUMMARY PAGE 4