<br /> PROJECT COST SUMMARY FEBRUARY 4, 1999
<br /> OPTION 1 - FOUR SEPARATE FIELDS
<br /> NORTH EUGENE HIGH SCHOOL @ EXISTING TRACK SITE
<br /> A B C D E F
<br /> BASIC BASIC FIELD ADD ADD ADD ALL
<br /> FIELD & UTILITY BLEACHERS ADDITIONAL RESTROOMS & FEATURES
<br /> COSTS SERVICES & LIGHTS COMPONENTS CONCESSIONS INCLUDED
<br /> BASIC FIELD COMPONENTS
<br /> 1 FIELD ENGINEERING $8,986 $8,986 $8,986 $8,986 $8,986 $8,986
<br /> 2 FIELD SURFACE AND DRAINAGE $942,737 $942,737 $942,737 $942,737 $942,737 $942,737
<br /> 3 CHAIN LINK FENCE AND GATES $22,619 $22,619 $22,619 $22,619 $22,619 $22,619
<br /> 4 PAVEMENT BETWEEN FENCE AND FIELD $151,683 $151,683 $151,683 $151,683 $151,683 $151,683
<br /> 5 WALKWAY BETWEEN PARKING AND FIELD $22,540 $22,540 $22,540 $22,540 $22,540 $22,540
<br /> 6 EMERGENCY AND SERVICE VEHICLE ACCESS $0 $0 $0 $0 $0 $0
<br /> 7 TRACK AND FIELD AMENITIES REPLACEMENT $36,520 $36,520 $36,520 $36,520 $36,520 $36,520
<br /> 8 GOAL POSTS $5,638 $5,638 $5,638 $5,638 $5,638 $5,638
<br /> I SUB -TOTAL BASIC FIELD COMPONENTS $1,190,723
<br /> BASIC UTILITY SERVICES ROUGH -IN
<br /> 9 ADD FIRE WATER UTILITY SERVICE $42,975 $42,975 $42,975 $42,975 $42,975
<br /> 10 ADD ELECTRICAL UTILITY SERVICE $34,720 $34,720 $34,720 $34,720 $34,720
<br /> I SUB -TOTAL BASIC FIELD COMPONENTS & UTILITY ROUGH -IN $1,268,418
<br /> ADDITIONAL PROJECT ENHANCEMENTS
<br /> ADD BLEACHERS AND FIELD LIGHTING
<br /> 11 ADD 1000 SEAT GRANDSTAND $194,703 $194,703 $194,703 $194,703
<br /> 12 ADD ELEVATOR TO OBSERVATION BOOTH $0 $0 $0 $0
<br /> 13 ADD FIELD LIGHTING $132,460 $132,460 $132,460 $132,460
<br /> I SUB -TOTAL BASIC FIELD COMP. & UTILITY ROUGH -IN & BLEACHERS & LIGHTING $1,595,581
<br /> ADD OTHER PROPOSED PROJECT AMENITIES
<br /> 14 ADD SCORE BOARD $23,312 $23,312 $23,312
<br /> 15 ADD ACOUSTICAL SOUND SYSTEM $18,794 $18,794 $18,794
<br /> 16 ADD DUMPSTER STORAGE AREA $6,172 $6,172 $6,172
<br /> I ADD ADDITIONAL COMPONENTS $1,643,859
<br /> ADD REST ROOM FACILITIES
<br /> 17 ADD RESTROOM FACILITIES $278.154 $278,154
<br /> 18 ADD CONCESSION BUILDING $72,899 $72,899
<br /> 19 ADD SANITARY SEWER UTILITY SERVICE $40,815 $40,815
<br /> 20 ADD DOMESTIC WATER UTILITY SERVICE $42,906 $42.906
<br /> I SUB -TOTAL FIELDS & UTILITY ROUGH -IN & BLEACHERS & LIGHTING & RESTROOMS S2,078,633
<br /> REMAINING PROJECT COMPONENTS
<br /> 21 ADD WALKWAY LIGHTING BETWEEN PARKING AND FIELD $63,267
<br /> TOTAL PROJECT COSTS FOR ALL PROJECT COMPONENTS $2,141,900
<br /> WBGS ARCHITECTURE PLANNING PC 2/4/99
<br /> PROJECT COST SUMMARY PAGE 3