• City of Eugene stormwater quantity and quality criteria dated <br /> August 21, 1995, included with the packet apply to the project. <br /> • Other agency requirements for drainage plans still to be received <br /> will also apply to the project. <br /> II. DISCUSSION OF DRAINAGE ELEMENTS <br /> A. Erosion Control <br /> Mr. Lyle stated that it was anticipated that a plan to mitigate down stream <br /> effects of excavation would be submitted. He asked that information about the <br /> erosion control plan of the project be provided to determine if a stormwater <br /> sewer line needed to be constructed earlier than planned. He recommended that <br /> a by pass be included in the stormwater pond system to avoid the need for them <br /> to be flushed out. <br /> Mr. Lyle raised questions about plans to control vehicle movement during <br /> construction to reduce impact on wetlands. Mr. Peebles stated that the <br /> concerns were addressed in early submissions and in responses to the DEQ. He <br /> said that additional information would be provided to the City. <br /> In response to questions of Mr. Alverson, Mr. Sabin noted that tests had <br /> determined that arsenic, lead, and chromium would not be leached into ground- <br /> water when disturbed by construction. He said that the information had been <br /> provided to the DEQ. <br /> In response to questions of Mr. 011ek, Mr. Peebles said that plans for <br /> movement of construction vehicles and placement of the excavation stockpile <br /> were being developed and would be provided to the City. <br /> Mr. Peebles stated that determination of whether separate permits could be <br /> issued for the planned construction staging area would be advantageous. Mr. <br /> Lyle stated that since the parcel would be leased, the separate permit would <br /> be required. <br /> Mr. Mills was identified as the City contact person with whom issues relating <br /> to off -site right -of -way development should be discussed. <br /> MINUTES -- Hyundai- Willow Creek October 26, 1995 Page 3 <br /> Drainage Pre - Design Meeting <br />