New Search
My WebLink
|
Help
|
About
|
Sign Out
New Search
Grant 669 No Cost Extension
COE
>
PW
>
Admin
>
Finance
>
Capital
>
2013
>
Grant 669 No Cost Extension
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
11/30/2012 9:25:24 AM
Creation date
11/30/2012 9:24:29 AM
Metadata
Fields
Template:
PW_Capital
PW_Document_Type_Capital
Correspondence
PW_Active
Yes
External_View
No
GL_Grant
669
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
4
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
Show annotations
View images
View plain text
or two until conditions are favorable. The contractor is scheduled to do this work in mid- <br />December, as soon as willow cuttings become available from local nurseries, however, if site <br />conditions are not suitable, getting the work done by December 31 may not be possible. By <br />extending the end date of this grant, it gives us the flexibility to accomplish the planting of these <br />8,000 cuttings. <br />Replanting Work to Meet Contract Requirements at Delta Ponds and Heron Slough. The two <br />older planting contracts that the City has for planting native trees, shrubs, sedges and rushes <br />under this grant required the contractor to achieve 80% plant survival at the end of the plant <br />establishment period. September 2012 survival monitoring by the City revealed that plant <br />survival did not meet the contract specifications and we are requiring the contractor to plant an <br />additional 3,322 plants at Delta Ponds and 1,740 plants at Heron Slough at no cost to the City. <br />While all of the plants for Delta Ponds and 900 of the plants for Heron Slough are cuttings, the <br />remaining 840 plants for Heron Slough are bare root trees and shrubs. The contractor has notified <br />the City that they will not be able to acquire these plants from nurseries until late January. <br />Extending the end date of our grant allows us to accommodate the late availability of plants in <br />order for the contractor to meet their obligations and receive final payments. <br />Water Quality Sampling in the Canoe Canal. The Fish Passage Feasibility Study for the Canoe <br />Canal is on schedule to be completed. However, following discussions with NOAA and ODFW, <br />we have added more extensive water quality sampling to the study. We are uncertain that this <br />st <br />can be accomplished for inclusion in the report before December 31, 2012. Extending the grant <br />end date will provide the flexibility to ensure that we have adequate time to complete this <br />important task and include the information in the final report. <br />7.Amount of the remaining unobligated funds, noting whether the funds will be expended <br />as originally proposed: <br /> If the work described above is not completed in December this <br />work represents $31,533 in funding. This money would be expended, for the work originally <br />proposed, by the new end date of March 31, 2013. <br />8.Budget for the work to be completed during the extension period using the categories <br />on the 424A (include a description and justification of both the Federal and non- <br />Federal shares): <br />Object Class Category FederalNon-FederalTOTAL <br />a. Personnel <br />b. Fringe Benefits <br />c. Travel <br />d. Equipment <br />e. Supplies <br />f. Contractual $31,533 $31,533 <br />g. Construction <br />h. Other <br />i. Total direct charges (sum of a-h) <br />j. Indirect charges <br />k. TOTALS (sum of i and j) $31,533 $31,533 <br />2 <br />
The URL can be used to link to this page
Your browser does not support the video tag.