• Coordinated with City staff regarding available GIS and mapping information. <br />• Prepared preliminary project mapping to support field investigations. <br />• Conducted initial site reconnaissance and bank stability assessment (January 27, 2011). <br />• Continued project management tasks. <br />Project work is on schedule. Fieldwork has been delayed slightly due to high Willamette River stages. When we visited <br />the site on January 27`e it was difficult to see much of the river bank and access to some areas was limited. We decided <br />it would be most productive to schedule our field investigations during more favorable weather and lower river stage. <br />We anticipate completing field investigations during this next week. <br />We anticipate working on the following tasks during February: <br />• Finish development of project GIS mapping and figures, <br />• Complete field investigations and measurements, <br />• Continue GIS analysis and assessment of existing bank stability conditions, <br />• Begin development of "areas of concern" mapping. <br />Eirik <br />Eirik Schulz, PE <br />Water Resources Engineer <br />VIGIL-.%K AGRIMIS <br />design professionals <br />819 SE Morrison Street, Suite 310 <br />Portland, Oregon 97214 <br />503-274-2010 <br />503-274-2024 fax <br />esch ulz@wgdagri m is.com <br />www.vigil-agrimis.com <br />Engineering . Landscape Architecture . Environmental Science <br />