CITY OF EUGENE DEPARTMENT OF PUBLIC WORKS <br />ENGINEERING DIVISION <br />Change Order Job # 4sos <br />Contract # 2010-007 CONTRACTOR: Eu ene Sand Construction Inc. Change Order # 1 <br />(ADDRESS) PO Box 1067 Date: 11110109 Eugene OR 97440 CAMS Date: <br />Reviewed by: Date: <br />PROJECT: Echo Hollow Tennis Court Overla Pro'ect Ins ector: Keith Jurasevich at 1655 Echo Hollow Road Const. Lead Kns Olson <br />Pro'. M r. David Stams Civil En . Teri Hf ins t <br />Principal End. Michelle Cahill You are directed to make the following changes in this contract: <br />Contract <br />Item No. <br />This chan a order will extend the on inai contract com letion date from November 2, 2009 to Jul 45 2040 due to weather conditions <br />that will not allow the work to take lace. The contractor a tees to hold the As halt Surfacin rice as bid with no increase. <br />100 The Surface cleanin item is re aired to resume this s tin . The contractor will ressure wash and clean the existin surface, and com fete rode <br />corrections to tolerances re aired b the s eci0cations and manufacturer's re uirements before a lication of the athletic surfacin can take lace. <br />This changes the bid items as follows: <br />Contract Contract Item Time Quantity Unit Amended Net <br />No. Item Change (Units} Cost Amount ~fl~} Change Change Ori inai 0,00 0.00 0.00 $0.00 <br />Revised 0.00 0.00 0,00 100 Surface Cleaning Amended 1.00 LS $800A0 $800.00 $800A0 <br />Ori inai 0.00 0,00 0.00 $0.00 <br />Revised 0.00 0,00 0.00 Amended 0.00 $0.00 $0,00 $OAO <br />Ori inai 0.00 0,00 0.00 $OAO Revised 0.00 0.00 0.00 <br />Amended 0,00 $0.00 $0.00 $OAO <br />Ori inai 0.00 0,00 0.00 $OAO Revised 0.00 0.00 0.00 <br />Amended 0.00 $0,00 $0.00 $0.00 Ori inai 0.00 0.00 0.00 $0,00 <br />Revised 0.00 0,00 0.00 <br />Amended 0,00 $0.00 $0.00 $0,00 Ori inai 0.00 0,00 0.00 $0.00 <br />Revised 0.00 0,00 0.00 Amended 0.00 $0.00 $0.00 $O.oO <br />The original contract work days are o.o da s <br />The contract time change this C.4 0.o da s <br />The contract time change by previous CA.'s 0.0 da s The new contract work da s are o.o days <br />The original contract sum was X92,990.00 <br />Net change by previous change arder ~o.oo <br />Net change due to amendmen# by previous change order X0.00 The contract sum prior to this change artier was $92,990.00 <br />This change order will change contract sum by this amount $800.00 The new contract net change sum ~o.oo <br />The new contract amendment sum $800.00 <br />The new contract sum including this change order will..~~ $93,790.00 Percenta a of ari inai contract 0.8610 <br />NET CHANGE: DUE TO AMENDMENTS 0.86/0 <br />Approval by: <br />City Engin er ~ Prime Contractor Third Party <br />~ <br />Date Date Date <br />CONTRACTOR ~ OFFICE FILE ~ PURCNASINGICRO <br />Q:IPROJECTSIPROJ-8146081CanstructionlChange Orders14608-20091110 Change Order1.xls <br />- <br />