Metropolitan Wastewater Management Commission Capital Programs <br />$527,000 carried over from previous years, brought the total budgeted for the project to <br />$1,227,000. Staff estimates that $250,000 will be spent in the current budget year, leaving <br />$977,200 to be carved over to FY 01-02. <br />3. Wet Weather Flow Management Plan FY 01-02 Capital Budget = $595,567 <br />The Wet Weather Flow Management Plan (WWFMP) was initiated in the FY 97-98 CIP in <br />response to Master Plan findings and recommendations concerning the ability of the WPCF to <br />handle peak wet weather flows. The WWFMP was. approved by the Commission in early 2001. <br />The WWFMP project budget of $1,150,000 includes two parts: 1) In FY 97-98 and FY 98-99, a <br />total of $500,000 was budgeted to prepare the WWFMP report, and 2) In FY 00-01, $650,000 <br />was budgeted for flow monitors, technical assistance and Glenwood pump station upgrade. Total <br />expenditures to prepare the WWFMP report are $487,597 which is $12,403 below the original <br />budget of $500,000. The estimated FY 00-O1 expenditure for the flow monitoring, technical <br />assistance and Glenwood pump station is $130,000. The remaining budget of $595,567 will be <br />carried into FY 01-02. Installation of the interceptor flow monitors is expected by late summer. <br />The Glenwood pump station upgrade will be the final aspect of this project. Capital <br />improvements to implement the regional component of the WWFMP will be budgeted and <br />tracked in the Peak Wet Weather Flow Improvements project. <br />4. Peak Wet Weather Flow Improvements FY 01-02 Capital Budget = $2,000,000 <br />The WWFMP, completed in FY 00-01, identifies a comprehensive 10-year capital improvement <br />program for peak wet weather flow management in the cities of Eugene and Springfield and at <br />the WPCF. Specific capital improvements needed at the WPCF to address peak wet weather <br />flow conditions include upgrading the primary treatment capacity to 263 mgd, upgrading the <br />secondary treatment capacity to 130 mgd, and expansion of outfall diffuser capacity. The total <br />cost of these improvements is estimated by CH2M Hill to be $33 million. <br />Because of the complexity of the recommended improvements, it will be necessary to perform an <br />engineering analysis of the impact and sequencing of each improvement. In FY 99-00, $607,500 <br />was budgeted fora preliminary design/engineering study of the raw sewage pumping and <br />secondary diversion gate improvements recommended in the Facilities Master Plan. Those funds <br />were carried forward into FY 00-01 and will be carried forward again into FY 01-02. Additional <br />funding, in the amount of $1,392,500 is proposed in FY 01-02 to provide a total of $2 million <br />initial funding for this project. Design of the secondary clarifiers and outfall expansion is <br />included in this project. <br />Page 27 FY 01-02 Budget <br />