New Search
My WebLink
|
Help
|
About
|
Sign Out
New Search
FY 2004-05 Regional Wastewater Budget and CIP
COE
>
PW
>
Admin
>
Execs
>
Executive non-confidential
>
Historical
>
FY 2004-05 Regional Wastewater Budget and CIP
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
6/9/2009 8:06:08 AM
Creation date
6/1/2009 12:28:11 PM
Metadata
Fields
Template:
PW_Exec
PW_Division_Exec
Wastewater
PWA_Project_Area
MWMC
PW_Subject
Budget & CIP
Document_Date
6/30/2005
External_View
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
84
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
Show annotations
View images
View plain text
Metropolitan Wastewater Management Commission Capital Improvements Program <br />Plant Predesign Study and Facilities Plan (Formerly -Plant Performance Improvements - <br />Predesign Study) <br />FY 04-05 Capital Budget = $200,000 <br />The predesign project evolved into a comprehensive Facilities Plan that establish RWP capital needs <br />through the year 2025. During FY 03-04, the project scope was modified to include determining <br />future use alternatives for the SIW facility, and to provide professional assistance with developing <br />SDC methodology alternatives. The $200,000 carried forward to the FY 04-OS budget will fund <br />actual predesign studies for the projects identified in the Facilities Plan as phase one projects. <br />Lab Modification <br />FY 04-05 Capital Budget = $45,000 <br />The Lab Modification project was essentially completed in FY 03-04. There are two remaining <br />issues: (1) exhaust fan vibration isolation system problems; and (2) acid neutralization system <br />problems that were identified during the later part of 2003. The funds carried forward to FY 04-OS <br />are intended to complete any remaining retrofits necessary for final resolution of any remaining <br />operational difficulties with the new lab facilities. <br />New Projects <br />The following projects address needs/projects identified in the WWFMP (2001) and the 2004 <br />MWMC Facilities Plan. <br />Digester Mixing Improvements <br />FY 04-OS Capital Budget = $2,000,000 <br />Expected cash flow:* FY 04-OS $660,000; FY OS-06 $1,340,000. <br />The 2004 Facilities Plan identifies the need to provide additional solids stabilization volume. This <br />project includes design and construction of digester mixing improvements that will increase the <br />active volume of the existing three digesters, thus allowing for additional solids stabilization volume. <br />This will be accomplished by replacing the existing gas mixing system with a pump mixing system. <br />This project will also defer the need to construct an additional digester. <br />Design work and the beginning of construction is planned for FY 04-05. The remaining construction <br />work is planned for FY OS-06. <br />Primary Clarifier Enhancements <br />FY 04-05 Capital Budget = $1,200,000 <br />Expected cash flow:* FY 04-OS $600,000; FY OS-06 $600,000. <br />The preferred alternative for treating peak flows in the 2004 Facilities Plan is called Parallel <br />Primary/Secondary Treatment. In this alternative, peak flows up to 130 million gallons per day <br />(mgd) will receive primary treatment in the primary clarifiers and be diverted around the aeration <br />basins and secondary clarifiers. Flows greater than 130 mgd will be treated in the aeration basins <br />and secondary clarifiers. The two flows will be blended back together and receive chlorine <br />disinfection before being discharged. The Primary Clarifier Enhancements project includes design <br />and construction of baffling in the primary clarifiers and removal of hydraulic restrictions. <br />Enhancing the existing clarifiers will increase primary treatment capacity, increase capacity to treat <br />Page 27 FY 04-OS BUDGET AND CIP <br />
The URL can be used to link to this page
Your browser does not support the video tag.