Change Order No. 11 $ 35,563.68 <br />$2,679,088.88 <br />D. Biosolids Irrigation Systems & WZ Pump Station Improvements -Project P80016 <br />The contract was awarded to James W. Fowler, Co. on November 6, 2003. Work began at the BMF sight in <br />February 2004. The construction project is 60% completed overall. <br />Contractor: James w. Fowler, Co. <br />Notice to Proceed: December 17, 2003 <br />Original Contract Amount: $2,194,430.00 <br />Change Order Na. 1 $ 3,612.30 <br />Change Order No. 2 $ 9,334.60 <br />Change Order No. 3 $ 3,983.16 <br />Change Order No. 4 $ 5,085.67 <br />Change Order No. 5 $ 1,440.10 <br />Change Order No. 6 $ 7,606.96 <br />Change Order No. 7 $ 14,887.65 <br />Change Order No. 8 $ 1,986.99 <br />Change Order No. 9 $ 28,625.63 <br />Change Order No. 10 $ 6,933.54 <br />Change Order No. I 1 $ 7,948.54 <br />Change Order No. 12 $ 24,278.56 <br /> $ 2,310,153.70 <br />E. Biocycle Farm _ Irrigation Hose Reels Purchase -Project P84017 <br />142VtTMC executed a contract with Familiar Narthwest for the amount of $172,681.84. Units were delivered <br />to 1VIWMC. Operation and Maintenance training has happened and they are working to complete systems <br />integration work. <br />Contractor: Familian Northwest <br />Notice to Proceed: October 6, 2003 <br />Original Contract Amount: $172,681.84 <br />Change Order No. 1 $ 9,361.00 <br />Change Order No. 2 $ 5,845.00 <br />p $187,887.84 <br />F. Biocycle Farm Phase One -Soil Preparation and Tree Planting -Project P80018 <br />MWMC awarded this contract to Greenwood Resources (Portland)., Site preparation has been completed, <br />and trees were planted in March/Apri12004. Contractor is substantially complete and is monitoring the new <br />trees. <br />Contractor: Greenwood Resources, Inc. <br />Notice to Proceed: August 26, 2003 <br />Original Contract Amount: $161,617.98 <br />Change Order No. 1 $ (7,200.00) <br />Change Order No. 2 $ 2,805.00 <br />$157,222.9$ <br />2 <br />