costs due to the negligence of the school district. 4J will provide both COE and FCC with <br /> advance notice in writin of an ~ <br /> g y projected cost over-runs. <br /> If Project Costs Including the Work is Less than Budget• <br /> If the Project costs including the Work is less than the budget, by more than $1,000, the <br /> contributions of COE and FCC will be reduced in the same proportion as their initial <br /> contribution, as follows: COE 56% and FCC 44%. <br /> DESIGN OF THE WORK: <br /> 4J will contract with Balzhiser & Hubbard Engineers (BHE) for the design of the Work. The <br /> design will be in conformance with the COE standards for privately engineered public <br /> improvement (PEPI) projects. <br /> CONTRACTING FOR THE PERFORMANCE OF THE WORK: <br /> 4J has contracted with Chambers Construction Company (CCC) to act as construction <br /> managers/general contractors for the Work. Based on an approved design, CCC wiiF <br /> competitively bid' the Work. Based on the- lowest responsive bid, a change order establishing <br /> a price agreement for the Work wi(i be executed with CCC. <br /> COE -Standard Contract Provisions: <br /> 1. 4J will include provision 1 -Fair Employment Practice Provisions <br /> (Eugene Code, 1971, Section 4.625) and provision 7 -Labor Contract <br /> Conditions (Eugene Code, 1971, Section 2.030) of the City of Eugene - <br /> Standard Contract Provisions in the subcontract for the Work. <br /> 2. 4J will include a clause in the subcontract for the Work that grants the <br /> City of Eugene the authority to monitor and enforce provisions 1 and 7 of <br /> the City of Eugene -Standard Contract Provisions. <br /> Bondinca: <br /> A bid bond and performance bond covering this Work will be provided by CCC. <br /> PROJECT MANAGEMENT: <br /> 4J will provide project management for the Work: 1) Bring BHE under contract for the <br /> design; 2) Bring CCC under contract for the Work; 3) Oversee the design and construction; <br /> 4) Process BHE's and CCC's payment requests; 5) Coordinate with COE and FCC with regard <br /> to the progress of the Work and COE's and FCC's payments to CCC; 6) Request County <br /> funds on a percentage of design and Work complete basis and make payment to CCC on the <br /> same basis. Final payment will be made when the Work is complete and accepted as <br /> meeting the requirements of the drawings and specifications; 7) Invoice County for the <br /> CDRIAF funds as needed; 8) Keep an accounting of all project expenditures. 4J will receive <br /> for it's project management 5% of the construction cost. <br /> Ru_cinninn- {anlnrAr 1+L,c:_.,~r+ie~. ~.~,.-e.z 1=.:4f_.fh:~. _ruun~ c-.:.~..... <br /> ~;a...a.._-..~~..~.~.~..a..._i.tc._ ..„.~._....,._-_-a~„~ <br /> School District 4J City of Eugene Faith Center Church <br /> Dire ~ of Facilities €i#y=pga~a~ Administrativ astor <br /> <br /> Date. ~ t,~ Date: ~ °3 Date: 7~~~~3 <br /> Public Works Director <br /> <br />