t,~Ly ~oniracz cuu4-uucl~ <br /> i July 18, 2003 <br /> MEMORANDUM OF UNDERSTANDING <br /> PARTIES: <br /> This is a Memorandum of Understanding (MOU) between School District 4J (4J), the City of <br /> Eugene (COE) and the Faith Center Church (FCC). <br /> SUBJECT: <br /> The MOU concerns the improvement of the unimproved portion of 14th Avenue, from, <br /> approximately, the 4J property line on the east, to Chambers Street on the west, hereafter <br /> called the Work. The improvement is a 28 feet wide street, with curbs, gutters, trees and <br /> lighting to meet City of Eugene Standards. <br /> i <br /> FINANCING: <br /> The cost of the Project is estimated to be $590,000, delineated as follows: Construction cost <br /> (1~Jork): $451,838, Soft costs: including design ($55,000), COE inspection ($16,000), 4) <br /> administration (a fixed $22,592) and contingency ($44,570), for a total of $138,162. <br /> I <br /> Lane County, Board of Commissioners, has approved School District 4J's request for <br /> $472,000 from the Community Development Road Improvement Assistance Fund (CDRIAF). <br /> The remaining funding, $118,000, is to be provided by the City of Eugene ($66,000) and <br /> Faith Center Church ($52,000). <br /> City of Eugene Funds: <br /> Upon the successful completion of the improvements, as designated by a certificate of <br /> substantial completion issued by the design consultant, and acceptance of the public <br /> ' improvements by the COE, at the request of 4J, COE will pay their portion in a check made <br /> out to the 4J in the amount of $66,000. <br /> j Faith Center Church Funds: <br /> Upon the successful completion of the improvements, as designated by a certificate of <br /> substantial completion issued by the design consultant, and acceptance of the public <br /> improvements by the COE, at the request of 4J, FCC will pay their portion in a check made <br /> <br /> i out to 4J in the amount of $52,000. <br /> Cost Overruns: <br /> i Soft Cost Overruns - If at any time during the course of design or construction, there is an <br /> j occurrence that will cause a soft cost overrun, the parties will meet and determine a course <br /> of action or agree to an allocation of costs exceeding the budget. <br /> Construction Cost-Overruns - If at bid opening the cost of the Work exceeds the budget <br /> i ($451,838) the' parties will meet and determine how to reduce the scope of-the Work to <br /> bring the project within it's budget or agree to an allocation of the costs exceeding the <br /> budget. If at any time during the construction phase of the project, there is an occurrence <br /> that will cause a cost overrun, the parties will meet and determine a course of action, or <br /> agree to an allocation of the costs exceeding the budget. <br /> If there is an overrun that requires an allocation, 4J will contribute up to $5,900 (5% of <br /> $118,000). 4J will have no other responsibility for extra construction costs, except those <br /> f <br /> _ _ _ _ <br /> 1 <br /> <br />