PROJECT BUDGET SUMMARY <br />Garden Wav Street Wldentna 8 Improvements <br />JN 3502 ORIGINAL OR <br />(circle one) <br />CURRENT FUNDING STATUS <br />Original Budget allocated to this project - - - - - - - - - - - - - - - $35,000.00 <br /> Assessments $35,000.00 <br /> Road $0.00 <br /> Sanitary Sew. $0.00 <br /> Storm Sew. $0.00 <br /> Subsidy $0.00 <br /> Other $0.00 <br /> Other $0.00 <br /> Other $0.00 <br />ESTIMATED CONSTRUCTION COSTS <br />Contractor(s): Wildish <br />Contract Amount - - - - - - - - - - - - - - - - - $2,079,450.75 <br />Contingency 6 % $124,767.05 <br />Total Estimated Costs - - - - - - - - - - - - - - - $2,204,217.80 <br />ESTIMATED ENGINEERING COSTS <br />Engineering Expenses to Date (PSF) - - - - - - - - - - - - - $522,000.00 <br />Estimated Engineering Expenses to Completion- - - - - - - - - - $130,000.00 <br />Total Estimated Engineering Costs - - - - - - - - - - - - - - - - $652,000.00 <br />~/~~~~ <br />REVISED <br />ESTIMATED ADMINISTRATION/SHORT TERM FINANCING <br />(use numbers from your assessment spreadsheet) <br />Admin. (5 % of assessable) - - - - - - - - - - - - - - - - $145,000.00 <br />Short Term Construction Financing - - - - - - - - - - - - - - $90,000.00 <br />Total Estimated Admin/Construction Financing- - - - - - - - - - - - $235,000.00 <br />ESTIMATED DIRECT COSTS <br />EWEB- - - - - - - - - - - - - - - - - - - - - $150,000.00 <br />Testing Expense Allocation - - - - - - - - - - - - - - - - $25,000.00 <br />ROW - - - - - - - - - - - - - - - - - - - - - $452,000.00 <br />Other Fees (Permits, Advertising, Prework, etc.) - - - - - - - - - - - - - - $26,500.00 <br />Consultant Fees - - - - - - - - - - - - - - - - - - - $15,000.00 <br />Total Estimated Direct Costs - - - - - - - - - - - - - - $668,500.00 <br />ESTIMATED TOTAL EXPENSES <br />Estimated Contract Cost - - - - - - - - - - - - - - - - - $2,204,217.80 <br />Estimated Engineering Costs - - - - - - - - - - - - - - - $652,000.00 <br />Estimated Admin/Financ./Direct Costs - - - - - - - - - - - - - - - - $903,500.00 <br />Total Estimated Project Costs - - - - - - - - - - - - - - - - - $3,759,717.80 -- <br /> REVISED FUNDING STATUS <br /> FUNDING SOURCE onstruct. Enoineer. <br /> Assessments $149,960.18 $44,357,70 <br /> Delayed Assessments $267,430.41 $79,104,99 <br /> On-HoIdWW Assessments $132,320.21 $39,139.86 <br /> Transportation SDC $1,153,400.71 $341,171,94 <br /> Wastewater SDC $6,952.58 $2,056,55 <br /> Storm SDC $209,594.20 $61,997.24 <br /> rterial Street Light (985314) $130,423.11 $38,578.70 <br />.)ry Q,r.S (iaY N` Traffic Signals (975024) $130,423.11 $38,578.70 <br />,, ~ <br />.. Ser. Far New Dev. (975124) $23,713.29 $7,014.31 <br /> TOTAL $2,204,217.80 $652,000.00 <br /> BUDGET RECOMMENDATION <br /> T e f ds are veil le, as shown above, to compl ]to th project. <br />~r <br />~ ro ct Manager ate <br /> FUNDS TO <br /> ShoR Term THIS <br />Direct Finance 5%Adm. PROJECT <br />$45,480.25 $6,123.00 $9,864.83 $255,785.96 <br />$81,106.88 $10,919.40 $17,592.37 $456,154.05 <br />$40,130.36 $5,402.74 $8,704.42 $225,697.59 <br />$349,805.89 $47,094.29 $1,891,472.83 <br />$2,108.59 $283.88 $11,401.60 <br />$63,566.19 $8,557.90 $343,715.53 <br />$39,555.01 $5,325.28 $213,882.10 <br />$39,555.01 $5,325.28 $213,882.10 <br />$7,191.82 $968.23 $38,887.65 <br />$668,500.00 $90,000.00 $145,000.00 $3,650,879.41 <br /> $3,7 7 .80 <br />me tat this project be done. <br />~~1\S ~~ ,W~,c, L'~C~.ui~=S <br />W wick. I`e tt!' Ck.s.-~ ~EC~.. <br />REMAINING <br />FUND <br />BALANCE <br />$0.00 <br />~O <br />Pr cipal E in er Date <br /> <br />q~3 ~ ~- <br />4/2,04 <br />`f <br />