M <br /> Attachment B: Schedule <br /> Task /Milestone Date <br /> Award of Contract February 24, 2004 <br /> Submittal to City for Review March 15, 2004 <br /> Submittal to FEMA March 26, 2004 <br /> Response from FEMA June 26, 2004 (based on standard 90-day turnaround time) <br /> Comments addressed July 15, 2004 (or within 21 days of FEMA response) <br /> <br /> Close of contract July 31, 2004 (or within 28 days of FEMA response) <br /> <br />