6of7 <br /> AIRPORT Eu ene Ai ort -Parallel DATE . 5/30/06 <br /> Runwa Pro'ect <br /> LOCATION Eugene, Oregon AIP PROJECT NO. 3-41-0018-35 <br /> Job No. 4183 <br /> CONTRACTOR Wildish Construction Co. Chan a Order 16 <br /> 2920 - Raise electrical vaults <br /> <br /> The two electrical vaults at the Hollis Lane crossing north of Taxiway Charlie were installed to match existing grades <br /> during the Phase I construction. After the ditches were filled on Hollis for safety reasons, these two vaults needed to be <br /> raised to match the revised grades. The existing buried vault on Taxiway Delta was discovered during recircuiting <br /> activities for the new SMGCS in this area. This vault needs to be accessible to airport operations, so it was raised to match <br /> existing grades. <br /> 2930 -Add sign switches <br /> Installing external switches on each new sign allows airport operations to locally turn off the power to each sign so that <br /> sign maintenance can be completed without having to turn off the complete sign circuit. This item was not included in the <br /> original project documents. <br /> 2940 - Regrade service roads in safety area <br /> The service roads that were constructed in the safety area need to have the shoulder filled and graded to meet the <br /> acceptable slopes in the safety areas. The roads were added on top of the original grade of the safety area and had up to 18- <br /> inches of depth that needed to be graded out to acceptable slopes. This work was not included in the original plans. <br /> 2950 -Additional grading around inlets on abandoned Rwy 3/21 <br /> In change order 13, the existing 15-inch thick layer of gravel base was excavated from the abandoned Runway 3 west of <br /> Runway 16R/34L to facilitate farming this area in the future. This work was left but of the original project and only <br /> specified that the asphalt was to be removed. To save costs associated with replacing this material, importing additional <br /> dill material, and putting the area back to the original grades, it was decided to flatten out the crown of the existing runway. <br /> This change order item was to take advantage of extra suitable fill material the contractor had on the site. The wntractor <br /> placed the extra material at his costs and the airport agreed to pay for the additional final grading'of this material to <br /> improve the drainage in this area. <br /> 2960 - Over~zcavation on Try M <br /> Unsuitable sub-grade was discovered during consh action of Taxiway M that had to be removed and replaced with baz-run <br /> rock in order to achieve the required compaction of the sub-base. This work was similar to the other over-excavation that <br /> had to be done under extra work on Taxiway C and other portions of Taxiway M. The project schedule could not wait to <br /> dry and work the wet soft clayey material. <br /> 2970 -Grade around basins at EGAR <br /> During construction of the two drainage basins north of EGAR, it was determined that the location and design of the inlets <br /> should be changed to improve the function and future maintenance. The original design had side inlets with steep slopes <br /> and after further investigation it was found that the inlets could be relocated to the center of the basins and that it would <br /> work must better. This grading was necessary to implement the change. <br /> 2980 -Paint additional Xs on the ends of Tzy B and Rwy 16L/34R <br /> The surface of the cement treated base on Taxiway B and Runway 16L/34R was tacked and aerial pictures revealed that a <br /> pilot could mistake the new cement treated base as usable pavements. These Xs were painted as an extra security measure <br /> to prevent pilots from landing on these facilities until they were completed and opened on September 1, 2005. <br /> 2990 -Install drain around fueling tank facility <br /> When the groundwater level in this area rises above the ground surface during the winter, it is possible for water to enter <br /> the transition sump, which is designed to collect secondary diesel oil spills. This drain was determined to be the least cost <br /> 6 <br /> <br />