Page 10 of 10 <br /> C HANG L O R D E R <br /> W12diah Job # 3237 <br /> City of Euqene Job # 4183 <br /> CHANGE ORDER: EV-07 <br /> PROJECT: Airport Runway <br /> Elect Vault Bldg <br /> <br /> The following changes are proposed: <br /> Reference Owner/Proj. RFI # 18. <br /> Three canopy mounting plates required a design <br /> change due to interferance with interior walls (see <br /> • RFI 18) . <br /> Gibson Steel: $ 900.00 <br /> Total Add/(Deduct} Costs This Change Order: $900.00 <br /> Total Above $900.00 <br /> Overhead & Profit (15~} $135.00 <br /> Proposed Change Order Cost $1,035.00 <br /> Recommended by <br /> Tim Bonn, Project Engineer Date : io/2~/2004 <br /> 10 <br /> <br />