<br />
<br /> Run Date: 09/19/2005 14:03:47
<br /> City of Eugene
<br /> Contract Preliminary Progress Payment
<br /> Payment No 016
<br /> Contractor: WILDISH CONST. Original Contract: $16,589,175.71
<br /> Job 93-004183 Current Amount: $16,914,394.33
<br /> Contract No: 2004-00024 Contract Award Date: 06/07/2004
<br /> PO 2004100581 Completion Date: 10/15/2006
<br /> Assessable: No
<br /> Current Contract Estimated Payment Cumulative Totals 8 Complete
<br />
<br /> Line Description Last Chng Ord Unit Price Unit Measure Quantity Amount Quantity Amount Quantity Amount
<br /> 0970 18 INCH STORM SEWER $39.00 LINFT 549.000 $21,411.00 0.000 $0.00 382.000 $14,898.00 70.00
<br /> 0980 24 INCH STORM SEWER $47.00 LINFT 163.000 $7,661.00 0.000 $0.00 150.000 $7,050.00 92.00
<br /> 0990 6-INCH UNDERDRAIN, COMPLETE $9.00 LINFT 2,000.000 $18,000.00 0.000 $0.00 2,000.000 $18,000.00 100.00
<br /> 1000 CATCH BASIN TYPE 5 $3,900.00 EACH 3.000 $11,700.00 0.000 $0.00 3.000 $11,700.00 100.00
<br /> 1010 REINFORCED CONCRETE INLET TYPE $1,300.00 EACH 1.000 $1,300.00 0.000 $0.00 1.000 $1,300.00 100.00
<br /> 1020 INLET COVER, TYPE A $438.00 HACB 1.000 $438.00 0.000 $0.00 5.000 $2,190.00 500.00
<br /> 1030 INLET COVER, TYPE B $730.00 EACH 3.000 $2,190.00 0.000 $0.00 2.000 $1,460.00 67.00
<br /> 1040 PIPE GRATE $450.00 HACH 2.000 $900.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 1050 SEEDING $70.00 ACRE 25.000 $1,750.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 1060 FERTILIZING ~ $400.00 TON 6.000 $2,400.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 1070 MULCHING $0.09 SQYD 122,000.000 $10,980.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 1080 5000 VOLT CABLE, N0. 8 $0.80 LINFT 98,780.000 $79,024.00 0.000 $0.00 98,000.000 $78,400.00 99.00
<br /> 1090 600 VOLT CABLE, NO. 6 $0.90 LINFT 7,200.000 $6,480.00 0.000 $0.00 7.000 $6.30 0.00
<br /> 1100 COUNTERPOISE, BARE NO. 6 $1.20 LINFT 37,155.000 $44,586.00 0.000 $0.00 37,000.000 $44,400.00 100.00
<br /> 1110 6 STRAND MULTIMODE FIBER OPTIC $2.40 LINFT 18,885.000 $45,324.00 0.000 $0.00 18,750.000 $45,000.00 99.00
<br /> 1120 COUNTERPOISH GROUND ROD $55.00 EACH 122.000 $6,710.00 0.000 $0.00 115.000 $6,325.00 94.00
<br /> 1130 CABLE MARKERS $100.00 EACH 10.000 $1,000.00 0.000 $0.00 9.000 $900.00 90.00
<br /> 1140 L-823 CABLB SPLICHS $47.00 EACH 12.000 $569.00 0.000 $0.00 45.000 $2,115.00 375.00
<br /> 1150 2" DUCT $1.40 LINFT 44,605.000 $62,447.00 0.000 $0.00 43,000.000 $60,200.00 96.00
<br /> 1160 DIRECTIONAL BORING CONDUIT $30.00 LINFT 1,465.000 $43,950.00 0.000 $0.00 1,465.000 $43,950.00 100.00