SPECIAL PROVISIONS FOR <br /> - 2008 PAVEMENT PRESERVATION PROGRAM <br /> MILL STREET ALLEY RCC FROM 12T" Ar/ENUE TO 13T" AVENUE <br /> JOB #4317 <br /> <br /> 00120.15 Examination of Work site and Solicitation Documents; Consideration of <br /> Conditions to be Encountered <br /> (ADD) Inquiries regarding the plans, specifications, and contract documents shall be <br /> made to: Matthew Rodrigues - (541) 682-6036 <br /> 00180.40 Limitation of Operations: <br /> (ADD) Preparation and testing of new RCC mix desi ns, including furnishing results of <br /> 28-day compressive a exural strength test the Engineer, shall be <br /> completed at least fourteen (14) a en ar days prior to beginning of on-site. <br /> excavation. <br /> (ADD) The Contractor shall complete the project no more than fourteen (L4) Calendar <br /> days after the first day of on-site excavation work. <br /> 00180.50 Contract Time to Complete Work . <br /> (c) Beginning of Contract Time <br /> (ADD) For Mill Alley Roller,Compacted Concrete Rehabilitation <br /> Work shall be completed by June 1, 2008. <br /> No weekend or holiday work will be allowed. <br /> 00180.85 Failure to Complete on Time: Liquidated Damages ' <br /> (b) Liquidated Damages , <br /> (ADD) Liquidated damages for this project will be $150 per a Calendar day. <br /> 00220.02 Public Safety and Convenience <br /> (ADD) The following bulleted item(s) to the end of this subsection: <br /> • Mill Alley between E. 12~' Avenue and E. 13"' Avenue may be closed to traffic <br /> for no more than four (4) consecutive Calendar days. Truck traffic will not be <br /> allowed on the RCC until seven (7) Calendar days after final compaction. <br /> • When construction requires the closure of a sidewalk or sidewalk ramp, place <br /> a Type "W1" "SIDEWALK CLOSED" (OR22-12-533) sign at each point of <br /> closure. Use a Type "W1" directional arrow (M6-1-381) rider, as needed, to <br /> direct pedestrian traffic. Mount each sign above the striped panel of a Type tl <br /> barricade placed across the sidewalk, facing pedestrians approaching the <br /> work area. Close the sidewalk at a point where there is an altemate way to > <br /> proceed or provide an altemate pedestrian route. <br /> Special Provisions -Job #4317 Page 1 of 26 <br /> <br />