w <br /> proposal to perform the work by "time and materials" where the City and Contractor would record the <br /> actual equipment, labor and materials spent on the work and use actual invoices and payroll to determine <br /> the cost of the work. After going through the records and receipts, the total cost to install the manhole is <br /> $16,217.23 which results in a 23.9% increase over the original contract amount. After the manhole was <br /> installed, Triad proceeded with the work under the original contract. <br /> After the work started in the channel, it was determined that the dewatering of the channel would prove <br /> more difficult than originally anticipated due to the excessive sediment build-up on the bottom of the <br /> channel. The original bid item for the dewatering work was $20,028. Again, Triad presented a summary <br /> of what they anticipated those additional costs to be, but we agreed to see what it would actually cost to <br /> perform the extra work. The original estimate submitted by Triad was $10,363. The actual amount agreed <br /> to in the change order is $2,625.01. <br /> After the bid, it was determined that signs to be permanently installed at the site were of a material that <br /> would difficult to maintain and it was agreed to change the sign material for a net cost reduction in the <br /> contract of $200 (original bid item was $1,500). <br /> The final item on the change order is the floating boom that floats across the Mill Race channel to prevent <br /> floatable debris from entering the City's stormwater system through the headgate. Originally, the boom <br /> was specified to be the standard color (orange) supplied by the manufacturer. Upon further discussion <br /> with Parks and Open Space, it was decided to change the color to black in order that the boom not look <br /> like an environmental hazard boom. The black material was more expensive (increase of $641.45), but <br /> would be more resistant to weather and prolong the life of the boom. Also, after the equipment began <br /> arriving on site, it was discovered that there were miscellaneous fixtures and structural attachments that <br /> were not delivered with the equipment nor shown on the original drawings that Triad was required to <br /> purchase to complete the installation. This work resulted in an additional cost of $1,137. <br /> Conclusion <br /> The original contract with Triad Mechanical was for $67,868. The change order is an increase of <br /> $19,779.24, or 29.14%, which results in a revised contract total of $87,647.24. <br /> Based on negotiations between Triad and the City and actual invoices and payrolls submitted by the <br /> Contractor, the costs on the change orders were determined reasonable and representative of the actual <br /> costs to perform the work. Due to the small size of the manhole work, it would not have been cost <br /> effective to perform the engineering tasks related to plan preparation, documentation and correspondence <br /> in order obtain additional proposals for this work. The remainder of the work would not stand on its own <br /> to be competitively bid and only resulted in a net increase of $3,562.01 or 5.2% over the original contract <br /> amount. None of this additional work results in favoritism in the award of, or diminishes competition for, <br /> future contracts. <br /> j , <br /> <br /> a~..~._ . .>~t. <br /> <br />