Medlin, Johnny <br /> From: CERMLGK <br /> Subject: BALLFIELD LIGHTING SCHEDULE <br /> Date: Tuesday, September 21, 1993 2:09PM <br /> FROM: RIS1(CERMLGK) <br /> TO: EUG001(CEWMJRM) DATE: 09 -21 -93 <br /> TIME: 14:13 <br /> CC: <br /> SUBJECT: BALLFIELD LIGHTING SCHEDULE <br /> PRIORITY: <br /> ATTACHMENTS: <br /> Date: 09/21/93 <br /> From: Louis Kroeck CERMLGK - RIS1 <br /> To: Dick Morgan CERMRAM - RIS1 <br /> John Etter CERMJFE - RIS1 <br /> Johnny Medlin CEWMJRM - EUG001 <br /> Subject: BALLFIELD LIGHTING SCHEDULE <br /> Trenching will begin at Ascot this week to install all underground <br /> conduits and then move to Graham probably the first week in October. <br /> After the underground work is complete at both fields then the remaining <br /> electrical service work will be done. <br /> The new poles and fixtures are scheduled to arrive and be install around the <br /> beginning of November. Once installed the wiring at Graham will be switched <br /> over from the old poles to the new ones and the old poles can then be removed. <br /> Page 1 <br />