~ CITY OF EUGENE <br />DEPARTMENT OF PUBLIC WORKS <br />ENGINEERING DIVISION <br />~''` <br />Change Order Job # 3502 <br /> Contract # 200420 <br />CONTRACTOR: Wtidish Construction Company Change Order # 5 <br />(ADDRESS) P O Box 7428 Date: 2/1812005 <br />Eugener OR 97401-0428 CAMS Date: <br /> Reviewed by. Date: <br />PROJECT: Paving, curbs, gutters, sidewalks. median, street lights, traffic signal, Inspector. John Bonham <br />street troea. wastewater. end storm water drainage on Garden WaY from Co r. r. Pal a Dickinson <br />Sisters View Ave. to Martin Luther fling Jr. Bid. north side of Martin Luther Proi. Mgr. Steve Gallup <br />King Jr. Blvd. from Marohe Chase Drive to I-b Principal Eng. Paul Klope <br />You are directed to make the following changes in this contrail: <br />Contract <br />Item' <br />No. <br />137 mo and re ace curb and utter at MLK BLVD to new vsrticle all nment <br /> <br />1380' move and re ce er wire and conduit for ODOT street I htln abn Garden Wa <br /> <br /> <br /> Ci'" 1~~~' ~ ~' ' <br /> , <br />(.O <br />,, <br /> 1J <br /> lJ <br /> <br /> <br />~ <br />~~ <br />~__ . <br /> <br />This ichanges the bid items as follows: <br />Contract <br />Contract <br />Item <br />No. .Item Time <br />Chan a Quantity <br />Units Unit <br />Cost <br />Amount <br />+/. Amended <br />Chan a Net <br />Chan e <br />1370 Mut curb & Sutter rem/repl Orl final 0.00 0.00 .00 ;0.00 <br /> Revised 0.00 0.00 .00 <br /> Amended 1.00 LS 1131.92 1131,42 1131.92 <br />1380 ODtJT Street iightlng replaoernent 0 foal 0.00 .00 .00 #0.00 <br /> Revised 0.00 .00 .00 <br /> Amended 1.00 LS 258.99 258.99 258.99 <br /> 0 anal 0.00 .00 .00 $0.00 <br /> Revised 0.00 0.00 .00 <br /> Amended 0.00 .00 .00 0.00 <br /> final 0.00 0.00 .00 $0.00 <br /> Revised 0.00 .00 .00 <br /> Amended 0.00 0.00 .00 .00 <br /> Ori final 0.00 .00 .00 ;0.00 <br /> Revised 0.00 .00 .00 <br /> Amended 0.00 .00 0.00 .00 <br /> Ori final 0.00 .00 .00 #0.00 <br /> Revised 0.00 .00 .00 <br /> Amended 0.00 .00 .00 .00 <br />The origtnal oontrad work days are o.o da a <br />The contrail time change this C.O o.o da s <br />The otxtbad time change by previous C.O: s o.o da <br />The new contract work da s are o.o da <br />The original contrail sum was .....".,..._........___"._._......_....._........_.._....."....._......__....."...."_".._."...__...".._......_....._._".._... <br />Net drartpe by previous change order .,,,~,,,„""„".,,,,,,_,"",.~,___~~, _, <br />Net ch{srf~e due to amendment by previous change order <br />".._.".._...._ ....................."..m.._..""....___...._.".. .................__... <br />The contract sum prior to this change order was ......................................"...._............................_................._......._.........._....._ <br />This change order will change contract sum by this amount ,,,.,,",".,,,",","„„,,,,,,,.",,,".,,,,_,,,~„_.__..,",",_,,,_ <br />The new contract net change sum <br />The new contract amendment sum ~~""""~"""~""""~"""""""~"~~ ~"""~" <br />the new Contrail sum InGuding this change order will be ,_..,,,,,__,,,~,,,,,.,,",,,",,,__~._,~ <br />Peroenta a of on anal contrail ................"....~...._........""....."...m.."~ <br />~~ E DUE TO AMENDM I,'N75 '~~~ ......-."........__..„...""_.._........."..._._. <br />Approval by: <br />City n ineer Ma.r'r. ~~-~ ~"S <br />3 <br />rate <br />LJ CONTRACTOR ^ OFFICE FILE <br />2.079.460.75 <br />t$1,34a.oo~ <br />$37,685.65 <br />$2,115,788.40 <br />$9,390.91 <br />x$1.348.00) <br />$47,076.58 <br />x2,125,179.31 <br />2.zo% <br />2.2ti9ro <br />Third Party <br />Date <br />QIFORMSIPROJECTICONSTIREVISED CHANGE ORDER.XLS <br />^ PURCHASING/CRO <br />