v1v <br /> / „ CITY OF EUGENE <br /> DEPARTMENT OF PUBLIC WORKS <br /> ENGINEERING DIVISION <br /> Change Order Job # a3os <br /> Contract # 2005-28 <br /> CONTRACTOR: Brown Contracting Inc. Change Order # 2 <br /> (ADDRESS) P.O. Box 26439 Date: 07/15/05 _ <br /> Eugene, OR 97402 CAMS Date: <br /> Reviewed by: Date: <br /> PROJECT: West University Neighborhood Alleys: #4, #9, #14, #24, Inspector: M. Koivula <br /> #26 #27 and #30 at 8 various locations in the area Construction Mgr. P. Dickinson <br /> generally bounded by Willamette St., 19th Avenue, Proj. Mgr. S. Gallu <br /> Kincaid St. and Franklin Boulevard Principal Eng. P. Kloae <br /> <br /> You are directed to make the following changes in this contract: <br /> <br /> Contract <br /> Item <br /> No. <br /> 172 Alle #4 -Remove & reconnect rivate 4" downs out drain to catch basin <br /> 173 Alle #4 -Form & our catch basin to with reinforcement to accommodate extra shallow storm lines <br /> 343 Alle #9 -Remove & re lace 4" WW line conflictin with storm line <br /> 640 le #24 -delete 4A curb inlet <br /> 772 Alle #24 south end -install 2.5A curb inlet around existin utilities <br /> 1391 Alle #30 north end -Under force account revise & fit storm lines to accommodate existin utilities. <br /> 1392 Alle #30 south end -Under force account revise & fit storm lines to accommodate existin utilities. <br /> Tinges the bid items as follows: <br /> Contract Contract <br /> hem Time Quantity Unit Amended Net <br /> No. Item Change (Units) Cost Amount Change Change <br /> 172 Alley #4 - Rem/Replace private 4" downspout Ori final 0.00 0.00 0.00 $0.00 <br /> drain 0 Revised 0.00 0.00 0.00 <br /> Amended 1.00 LS $538.88 $538.88 $538.88 <br /> 173 Alley #4 -Form and pour CB top w/reinfordng Orl final 0.00 I 0.00 0.00 $0.00 <br /> 0 Revised 0.00 0.00 0.00 <br /> Amended 1.00 LS 398.73 $398.73 $398.73 <br /> 343 Alley #9 -Remove and replace 4" WW line Ori Inal 0.00 0.00 .00 $0.00 <br /> 0 Revised 0.00 0.00 0.00 <br /> Amended 1.00 LS $1551.42 $1,551.42 1551.42 <br /> 640 Alley #9 Delete 4A Curb Inlet Ori final 1.00 EA 1500.00 1 500.00 (31,s~•~) <br /> 0 Revised 0.00 I 0.00 .00 ~l~ 8~,10Dd, <br /> Amended 1.00 $0.00 $0.00 <br /> 772 Alley #24 - stone drain changes Ori final 0.00 ' 0.00 0.00 $0•~ <br /> 0 Revised 0.00 0.00 0.00 <br /> Amended 1.00 EA $1949.20 $1949.20 $1949.20 <br /> 1391 Alley #30 -Cut and remove ex. lines for SD Ori final 0.00 0.00 0.00 $0.00 <br /> 0 Revised 0.00 I 0.00 0.00 <br /> Amended 1.00 LS 54.64 $454.64 54.64 <br /> 1392 Alley ;r30 - OT force acct. work for SD changes Orl Inal 0.00 .00 .00 $0•~ <br /> 0 Revised 0.00 0.00 .00 <br /> / y S~ Amended 1.00 LS $1 163.12 $1 163.12 $1 163.12 <br /> The original contract work days are o.o da ~ ~ S~~y f ~do~ed l`'e Co,.-f~G~7R. 5~ <br /> The contract time change this C.O o.o da a ~~s # <br /> The contract time change by previous C.O.'s o.o da S ~ ~ C' hf?n5 c ~t~v ~f <br /> The new contract work da are o.o da <br /> The original contract sum was 3310,294.00 <br /> Net change by previous change order 30.00 <br /> Net change due to amendment by previous change order 32,020.32 <br /> The contract sum prior to this change order was 3312,314.32 <br /> . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br />. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br /> This change order will change contract sum by this amount , 3a,555.ss <br /> The new contract net change sum - 31 500.00 <br /> The new contract amendment sum 38,076.31 <br /> . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br />. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br /> The new contract sum including this change order will be S7Q. 3 3316,870.31 <br /> Percents a of on final contract 2.12% <br /> 2.6090 <br /> NET HAN E DUE AMENDMENTS <br /> Approval by: <br /> City gineer Prime Contractor Third Party <br /> Date Date Date <br /> CONTRACTOR ~ OFFICE FILE ~ PURCHASING/CRO <br /> O\FORMS\PROJECT\CONST\REVISED CHANGE ORDER.XLS <br /> <br />