CITY OF EUGENE <br /> DEPARTMENT OF PUBLIC WORKS <br /> ENGINEERING DIVISION <br /> Change Order Job # a311 <br /> Contract # 2007-15 <br /> CONTRACTOR: Wildish Construction Co. Change Order # 2 <br /> (ADDRESS) P.O. Box 7428 Data: 05/23/07 <br /> Eugene, OR 97401 CAMS Date: <br /> ReNewed by: Date: <br /> PROJECT: Glenwood Boulevard Extension at Judklns Point south Inspeclar: R. Foss <br /> Interchange on Interstate 5 <br /> Prof. Mpr. I 'n Y\ <br /> Principal Eng. M. Cahill <br /> You are directed to make the following changes In this contract: <br /> Contract <br /> lum <br /> No. <br /> 810 Move wastewater manhole 15508 to Sts 8+32.29 15.81' RT <br /> 820 Conafnrd new Stomf manhole at a roximatel 1+50 50' ri ht and connect to existln 12" & 24" i es <br /> 830 Construct 24"ADS stone i e from new stone manhole to i oudalt <br /> 840 Construct La Storm Drain OuHall <br /> 280 Delete 8W Item 280 -Storm Water Outfall <br /> This changes the old items as follows: <br /> Contract Contract <br /> Item Time Quantity Unlt Amended Net <br /> No. Item Change Units Cost Amcunt +l- Chan a Change <br /> 610 Move W W MH 15508 to Ste 8+32.29 0 Orl final 0.00 ;0,00 <br /> Revised 0.00 <br /> Amended 1.00 LS 4 673.00 4 673.00 ;4 673.00 <br /> 620 Construd Storm MH 1+50 Ori Inal 0.00 0.00 0.00 ;0.00 <br /> Revised 0.00 0.00 0.00 <br /> 0 Amended 1.00 LS 3600.00 3600.00 3600.00 <br /> 630 Storm Drain Pipe, 24" ADS Orl Inal 0.00 0.00 0.00 ;0.00 <br /> Revised 0.00 0.00 0.00 <br /> Amended 180.00 FT 69.00 12 420.00 12 420.00 <br /> 640 Construct Large Stortn Drain Outfall OrI anal 0.00 0.00 0.00 ;0.00 <br /> Revised 0.00 0.00 0.00 <br /> Amended 1.00 LS 6 500.00 6 500.00 6 500.00 <br /> 280 Delebe Bid Item -Storm Water Outfall Orl final 4.00 FA 2 000.00 8 000.00 (;8,000.00) <br /> Revised 0.00 0.00 0.00 <br /> Amended 0.00 ;0.00 ;0.00 0.00 <br /> Ori anal 0.00 0.00 0.00 ;0,00 ~ <br /> Revised 0.00 0.00 0.00 ~ <br /> I <br /> Amended 0.00 ;0.00 0.00 ;0.00 <br /> W <br /> The original contract work days are o.o da s I <br /> The contract time change this C.O o.o da <br /> The contract time change by previous C.O's 0.0 da ~ <br /> The new contract work da are o.o da n <br /> The original contract sum was 5852,489.00 G~ <br /> Net change by previous change order (57,000.00) <br /> Net change due to amendment by previous change order 537,000.00 rv <br /> The contract sum prior to this change order was <br /> 5882.469.00 <br /> This change order will change contract sum by this amount <br /> 59,847.00 <br /> The new contract net change sum (515.000.00) z <br /> The new contract amendment sum 554,847.00 <br /> The new contract sum including this change order will be 58s2,31e.oo <br /> Percents a of on final contract 4.87% <br /> NET CNAN AM NDME 6.43% <br /> <br /> Approval by: / / <br /> r Fro t0. ut. <br /> City Engine r Prime Co actor Third P <br /> r 3~0, ~-~za/d7 <br /> Date Date Date T <br /> ? CONTRACTOR ? OFFICE FILE ? PURCHASING/CRO <br /> O\FORMShPROJECT\CONSTREVISED CHANGE ORDER.XLS <br /> 0 <br /> <br />