Synthetic Turf Fields Projected Cost Allocations <br />2/3/2009 <br />Combined Fields <br />Spencer Butte <br />Jefferson ATA <br />ATA Track/D surface <br />Sitework <br />1,564,490 <br />930,990 <br />633,500 <br />337,500 <br />'Sitework Change Orders to Date <br />293,216 <br />189,949 <br />103,267 <br />Forecast Change Orders <br />20,000 <br />0 <br />20,000 <br />Turf <br />681,961 <br />335,476 <br />346,485 <br />Turf Change Orders to Date <br />31,048 <br />15,524 <br />15,524 <br />Forecast Change Orders <br />35,000 <br />35,000 <br />Lighting <br />226,420 <br />113,210 <br />113,210 <br />No Change Orders <br />Wetlands Mitigation 2 <br />53,500 <br />3,500 <br />50,000 <br />65,500 <br />Nike Grant <br />-70,000 <br />Subtotal Construction: <br />2,905,635 <br />1,623,649 <br />1,281,986 <br />333,000 <br />Testing and Inspection PSI <br />14,515 <br />7,515 <br />7,000 <br />Gmax Testing - BioMechanica <br />2,190 <br />Consultant Fees: <br />Pivot Architecture <br />200,000 <br />100,000 <br />100,000 <br />7,500 <br />Balzhiser Hubbard Engineers <br />17,904 <br />8,952 <br />8,952 <br />Terra Science Wetlands Consultant <br />21,780 <br />10,000 <br />11,780 <br />Miscellaenous <br />14,816 <br />1,275 <br />City Permits/SDCs <br />21,456 <br />7-,202 <br />14,254 <br />State Permits/Fees <br />5,266 <br />1,871 <br />3,395 <br />338 <br />Subtotal Project <br />3,203,562 <br />Administration at 5% <br />160,178 <br />TOTAL <br />3,363,740 <br />342,113 <br />City Costs (New Fields) <br />1,681,870 <br />(City recently invoiced for $1,448,446, balance to be billed later.) <br />City Costs (Completed Fields) <br />666,405 <br />Total City Costs (SB/Jeff MS's) <br />2,348,275 <br />Outstanding cost Cal Young/Madison <br />41,0002 <br />NOTES <br />We are working through how to best protect lighting wiring from theft. Costs to protect wiring are not forecasted in this estimate. <br />Will need to reconcile costs to increase the length of the field at SBMS. (COE cost should go down.) <br />1. One acre (out of 2.31 acres) of mitigation at Jeff/ATA shared by City at $50,000 per acre. <br />2. We still hold $82,000 on the Sprinturf contract for Cal Young and Madison. We are holding $59,000 for 10 years of maintenance <br />on the four high school fields as a negotiated settlement for liquidated damages. Upon replacement of the turf at the high schools, <br />we would probably release some, or all of the $59,000. We also hold $10,000 for some sitework, which is complete. Finally <br />we are holding $13,000 until Sprinturf supplies acceptable warranties for the Cat Young and Madison fields. Part (or all) of these <br />costs will likely billed at a much later date. <br />