CHANGE REQUEST/PROCEED ORDER <br />1993-2008 Capital Improvement Program <br />Eugene School District 4J <br />CHANGE REQUEST NOTICE <br />Notice No.: 2 - Lengthen Field <br />Project No.: CIP 410.682.760 Contract No.: Date: July 10, 2008 <br />Project Title: 4J MS Athletic Fields Site Improvements - Turf Package <br />Contractor: Specialty Surfaces International Inc d/b/a Sprinturf <br />1. REQUEST INFORMATION <br />Estimated 7.750.00 Time: 0 Days: 0 Initiated by: PIVOT Architecture <br />Reason for change: The length of the field described in the contract documents needed to be Ieninhened This was coordi- <br />nated after the original extent of turf was shipped therefore additional turf needed to be fabricated delivered and installed <br />2. DESCRIPTION <br />Describe changes: Provide an additional roll of turf and related elements to add approximately 18" to the field at each end <br />Describe affected work: Installation of synthetic turf <br />List plan and spec sections: Section 02790 - Synthetic Turf, and Sheets A3 1 <br />Describe impacted activities: Delivery and installation of additional turf <br />Comment: - <br />3. DATES <br />Need for change first known: September 24, 2008 By whom: Installer <br />Contractor first notified: Sept 24 2008 How: During field installation <br />Owner first notified: September 24, 2008 <br />Date approved or rejected: By whom: P. R~(&,M7 <br />4. RECOMMENDATION (cost and time) $7.75 <br />0 <br />PROCEED ORDER <br />PROCEED ORDER NO.: Date: 5 J el <br />PAYMENT/COST <br />Actual amount of change $7,750 <br />Contractor amount $7,750 <br />Subcontractor amount $0 <br />Type of payment (LS/T&M) LS <br />2. MISCELLANEOUS <br />Subcontractors involved: None <br />Major materials: Synthetic Turf <br />(7,75-x'• no <br />The contract time will be: <br />( ) increased ( ) decreased by <br />( x ) will remain unchanged <br />days <br />The contractor is directed to proceed with the work, <br />The cost is not to exceed $_7 ,750 Date: <br />3 CHANGE REQUEST~CCEPTED BY: <br />Contractor: A / , <br />Architect: <br />4J CIP Proje Manager: <br />4J CIP Program Manager' mob- r'~ <br />4J Facilities Director: <br />~a47~ <br />Date: <br />Date: ,Q <br />Date: <br />Date: S <br />'Date: 1 <br />Without the signature of Facilities Director, or the acting Director, this Proceed Order is neither accepted or authorized, except by <br />written authorization of other specific delegation. <br />