CITY OF EUGENE <br />DEPARTMENT OF PUBLIC WORKS <br />ENGINEERING DIVISION <br />Change Order <br />CONTRACTOR: Babb Construction Co. dba Delta Construction Co. <br />(ADDRESS) 999 Division Avenue <br />Eugene O 97404 <br />PROJECT: Crest Nei ghborhood Street Improvement Project ^- <br />You are directed to make the following changes in this contract: <br />Contract <br />Item <br />No. <br />Job # <br />4546 <br />Contract # <br />2009 -030 <br />Change Order # <br />9 <br />Date: <br />05/31110 <br />CAMS Date: <br />The new contract work days are 0.0 da s <br />Reviewed by: <br />Date: <br />Inspector: <br />T. Fahsbender /J. Pinkham <br />Proj. Mgr. <br />J. Willer <br />Principal Eng. <br />P. Klo ' <br />781 Re- Excavate STA 18 +20 -18 +90 Ri ht on Storey Blvd as directed in the field Force Account 411 5120 1 0 <br />782 Re- Excavate STA 1 +70 - 3 +70 on Frilendly Street as directed in the field Force Account 5/14/2010 <br />811 Install temp oraU storm p1pe STA 18 +20 -18 +90 (Right) Storey Blvd as directed in the field Force Account 4/16/201 <br />881 l investigate existing storm and wastewaters stem at approx STA 11 +50 on Friendly St as directed in the field Force <br />951 Place 5 -7" Open Graded Rock in Over- Excavated Area STA 3 +20 - 3 +50 on Friendly St as directed in the field Forc <br />A Two additional da s will be added to the Contract Completion Time for this Contract as a result of this Contract Chai <br />:: ]n 2010 exce t lantin s and establishment shall be complete by October 4,.2010. There is no chance to tl <br />This changes the bid items as follows: <br />Contract <br />Item <br />No.. Item <br />781 Re- Excavate STA 18 +20 -18 +90 (Right) <br />Storey Blvd. on 4/15/2010 <br />782 Re- Excavate STA 1 +70 - 3 +70 Friendly Street <br />on 5/14/2010 <br />811 Install Temporary Storm Pipe STA 18 +20 -18 +90 <br />( Right) Storey Blvd on 4/16/2010 <br />881 Investigate existing storm and wastewater <br />stem at approx. STA 11 +50 Friends on 4/1/10 <br />951 Place 5 -7' Open Graded Rock In Over- Excavated <br />Area STA 3+20-3+50 Friendiv St on 5/7/2010 <br />Account 4111201 <br />as follows: The Stage to be com fete <br />completion date of October 20 20 1 0 . <br />Orig <br />Quantity <br />(Units) <br />0.00 <br />Unit <br />Cost <br />$0.00 <br />Amount <br />$0.00 <br />+1 -) <br />Revised <br />0.00 <br />$0.00 <br />$0.00 <br />The new contract work days are 0.0 da s <br />Amended <br />Original <br />1.00 LS <br />OAO <br />$380.17 <br />$0.00 <br />$380.17 <br />10.00 <br />- ............. ����������������� "�� "������� <br />Net change by previous change order ................ <br />Revised <br />0.00 <br />$0.00 <br />$0.00 <br />$2,158, <br />Amended <br />Original <br />1,00 LS <br />0.00 <br />$4,855.58 <br />$0.00 <br />$4,855.58 <br />$0.00 <br />... ..... ................._......., <br />Th e new contract amendment sum ..... .... ........................ <br />Revised <br />0.00 <br />0.00 <br />$0.00 <br />2.10% <br />Amended <br />Orig inal <br />1.00 LS <br />0.00 <br />$662.90 <br />$0.00 <br />$562,90 <br />0.00 <br />Revised <br />0.00 <br />$0.00 <br />$0.00 <br />Amended <br />Ori inal <br />1.00 LS <br />0.00 <br />.$451.03 <br />$0.00 <br />$451.03 <br />$0.00 <br />Revised <br />0.00 <br />0.00 <br />0.00 <br />Amended <br />Original <br />1.00 LS <br />0.00 <br />$390.53 <br />$0.00 <br />380.53 <br />10.00 <br />Revised <br />0.00 <br />$0.00 <br />$0.00 <br />Amended <br />0.00 <br />$0.00 <br />$0.00 <br />Amended Net <br />Change Change <br />$0.00 <br />$380.17 <br />$0.00 <br />5.58 <br />$0.00 <br />2.90 <br />$0.00 <br />1.03 <br />$0.00 <br />0.53 <br />$0.00 <br />The original contract work days are 0.0 days <br />The contract time change this C.4 0.0 days <br />The contract time change by previous C.O.'s 0.0 day <br />The new contract work days are 0.0 da s <br />The original contract sum was ..................... <br />$2 <br />- ............. ����������������� "�� "������� <br />Net change by previous change order ................ <br />$0.00 <br />N et change due to amendment by previous change order <br />$37,757.22 <br />The contract sum prior to this change order was <br />" .................................................- <br />$2,158, <br />..,�,�.,�........- .�.- ....�.... <br />This change order will change contract sum by this amount <br />$6,740.21 <br />. ................... .. .................... ............................... I .................. ........ �.. <br />Th e new contract net change sum <br />- $0.00 <br />... ..... ................._......., <br />Th e new contract amendment sum ..... .... ........................ <br />$44,4x7 43 <br />....... ... . ........................................................................ _ ... - .... _....��......... . <br />The new contract sum including this change order will -be <br />$2,184,904.63 <br />P ercentage of on final contract <br />2.10% <br />NETCHANGE DUE TO AMENDMENTS ......................................................................................_,.....,.......,............... ............................... <br />2.10 °!° <br />Approval by: <br />City Engineer <br />Date <br />F1 CONTRACTOR <br />Prime ContractY Third Party <br />Date Date <br />OFFICE FILE PURCHASINGICRO <br />llcesrv 6i45461ConstructionlChange Orders14546 Change Order 9.xlsx <br />Contract <br />Time <br />Chance <br />