EUGENE SAND CONSTRUCTION <br />GENERAL ESTIMATE SUMMARY <br />PRICE AGREEMENT <br />PROJECT LOCATION: <br />FILENAME: <br />City of Eugene - per Doug Ruebell <br />Pricing per - Dig Point Repair Project, #2007-00406 <br />Asphalt Removal @1359 Patterson Str. <br />job #430450.5 <br />phase codes; 50.160, 50.263, 50.400, 50.520 <br />1 1 1 <br />UNIT PRICES REVISED PER 4/09 AMENDMENT #3 <br />CADocuments and Settingslmbroadswi 8:42 AM <br />ITEM <br />DESCRIPTION BID UNIT <br />UNIT BID <br />TOTAL BID <br />QUANTITY <br />1 <br />Pick-up (1/2 ton) <br />Z.U <br />HK <br />:51umu <br />4)32S.uu <br />2 <br />1 ton Utility Crew Truck <br />0.0 <br />HR <br />$23.00 <br />$0.00 <br />3 <br />Backhoe 580/Operator <br />0.0 <br />HR <br />$77.00 <br />$0.00 <br />4 <br />Backhoe/Whacker 580/Operator <br />0.0 <br />HR <br />$96.00 <br />$0.00 <br />5 <br />Trackhoe/Operator (40,000 JD 490 <br />2.0 <br />HR <br />$101.00 <br />$202.00 <br />6 <br />Trackhoe/Operator (50,000 JD 590 <br />0.0 <br />HR <br />$116.00 <br />$0.00 <br />7 <br />Trackhoe/Opeartor (60,000 JD 690 <br />0.0 <br />HR <br />$126.00 <br />$0.00 <br />8 <br />Trackhoe/Operator (70,000 JD 892 <br />0.0 <br />HR <br />$141.00 <br />$0.00 <br />9 <br />Dozer D3/Operator <br />0.0 <br />HR <br />$91.00 <br />$0.00 <br />10 <br />Dozer D5/Operator <br />0.0 <br />HR <br />$109.00 <br />$0.00 <br />11 <br />Dozer D7/Operator <br />0.0 <br />HR <br />$188.00 <br />$0.00 <br />12 <br />Huber/Operator <br />0.0 <br />HR <br />$82.00 <br />$0.00 <br />13 <br />Grader 120 G/Operator <br />0.0 <br />HR <br />$87.00 <br />$0.00 <br />14 <br />Grader 140 G/Operator <br />0.0 <br />HR <br />$95.00 <br />$0.00 <br />15 <br />Water Truck/Driver <br />0.0 <br />HR <br />$75.00 <br />$0.00 <br />16 <br />6-8 ton Asphalt Vib. Roller/Operator <br />0.0 <br />HR <br />$9900 <br />$0.00 <br />17 <br />Wheel Loader, 2 yd/Operator, JD 544 <br />0.0 <br />HR <br />$92.00 <br />$0.00 <br />18 <br />Wheel Loader, 3 yd/Operator, JD 644 <br />0.0 <br />HR <br />$94.00 <br />$0.00 <br />19 <br />5 yd Dump Truck/Operator <br />0.0 <br />HR <br />$74.00 <br />$0.00 <br />20 <br />10 yd Dump Truck/Operator <br />5.0 <br />HR <br />$76.00 <br />$380.00 <br />21 <br />10 yd Dump Trk. W/Pup Trlr./Operator <br />0.0 <br />HR <br />$82.00 <br />$0.00 <br />22 <br />Roto-Miller <br />0.0 <br />SY <br />$6.11 <br />$0.00 <br />23 <br />Move Truck & Trailer/Operator <br />1.5 <br />HR <br />$82.00 <br />$123.00 <br />24 <br />Rented Dump Trucks <br />0.0 <br />HR <br />$75.00 <br />$0.00 <br />25 <br />By-Pass Pump, 3" outlet <br />0.0 <br />HR <br />$17.00 <br />$0.00 <br />26 <br />De-Watering Pump 2" outlet <br />0.0 <br />HR <br />$17.00 <br />$0.00 <br />27 <br />De-Watering Pump 4" outlet <br />0.0 <br />HR <br />$27.00 <br />$0.00 <br />28 <br />Trench Box <br />0.0 <br />HR <br />$16.00 <br />$0.00 <br />29 <br />Manhole box <br />0.0 <br />HR <br />$16.00 <br />$0.00 <br />30 <br />Labor, Straight Time <br />18.5 <br />HR <br />$41.75 <br />$772.38 <br />31 <br />Flagging <br />0.0 <br />HR <br />$32.00 <br />$0.00 <br />32 <br />3/4" - 0 Crushed Rock <br />6.20 <br />TON <br />$7.10 <br />$44.02 <br />33 <br />1 1/2" - 0 Crushed Rock <br />0.0 <br />TON <br />$710 <br />$0.00 <br />34 <br />3"-0 Crushed Rock <br />0.0 <br />TON <br />$7.60 <br />$0.00 <br />35 <br />C.D.F. <br />0.0 <br />CY <br />$75.00 <br />$0.00 <br />36 <br />Cl. "C" Asphalt <br />0.00 <br />TON <br />$49.80 <br />$0.00 <br />37 <br />4" 3300 psi Concrete (Compl. In-Place) <br />0.00 <br />SF <br />$5.10 <br />$0.00 <br />38 <br />5" 3300 psi Concrete (Compl. In-Place) <br />0.00 <br />SF <br />$6.30 <br />$0.00 <br />39 <br />7" 3300 psi Concrete (Compl. In-Place) <br />0.00 <br />SF <br />$7.40 <br />$0.00 <br />98 <br />Asphalt Sawcutting, approx. 0 If @ 4" depth <br />0.0 <br />IN-LF <br />$0.23 <br />$0.00 <br />99 <br />Concrete Sawcutting, approx. 0 If @ 6" depth <br />0.0 <br />IN-LF <br />$0.75 <br />$0.00 <br />100 <br />Silt Fencing <br />0.0 <br />LF <br />$0.75 <br />$0.00 <br />AMENDMENT #2 ITEMS <br />1 <br />Asphalt Paving Machine Blaw Knox PF500 <br />0.0 <br />HR <br />$164.00 <br />$0.00 <br />1 <br />$0.00 <br />TOTAL ES&O WORK <br /> <br />$1,559.40 <br />OUTSIDE MATERIALS & SERVICES: <br />Pioneer Concrete Cutting <br />1.0 <br />LS <br />$381.30 <br />$381.30 <br />American Barricade <br />10 <br />LS <br />$175.70 <br />$175.70 <br />Wildish Sand & Gravel -Cold Mix <br />2.75 <br />tons <br />$67.75 <br />$186.31 <br />0.0 <br />LS <br />$0.00 <br />$0.00 <br />$743.31 <br />10% <br />$817.64 <br />TOTAL PROJECT............ $2,377.04 <br />