00620.40 Pavement Removal: <br />(a) General <br />(ADD) Contractor shall lower all Manholes and complete pipe work and curb repair prior <br />to other work. <br />(d) Pavement Removal Alternative <br />(ADD) The Contractor shall provide a milling and paving: plan to the engineer 7 days <br />prior to beginning work. <br />(ADD) Wedges shall be placed at all intersections, points of beginning and end of milling <br />operation on the same Work day as the cold plane pavement removal. No traffic <br />will be allowed to cross drop-offs of more than two (2) inches without wedges in. <br />place. <br />00620.43 Maintenance Under Traffic <br />(ADD) Areas of 4' Cold Plane Pavement Removal shall be paved back to within 2" of <br />finished grade prior to the end of the work day. If areas of 3" Cold Plane <br />Pavement Removal cannot be paved on the same day as the pavement removal, <br />tapers must be constructed at all intersections and driveways and transitions to <br />other surfaces greater than 2". <br />00745.00 Scope <br />(ADD) All asphalt paving Work for this contract shall be Warm Mixed Asphalt Concrete <br />(WMAC). <br />00745.48 (c) Placing <br />(DELETE AND REPLACE) <br />In the last paragraph the words "less than 11 feet wide or less than 15 feet long" <br />with "small and irregular". <br />00745.62 (a),(1) Temporary End Panel <br />(ADD) At Transverse joints with a drop off of 3", construct a 12 foot long wedge (1V:50H <br />taper rate). <br />00745.90 General <br />Pay Item Unit of Measurement <br />(c) Level , WMAC, <br />00748.90 Payment <br />(ADD) Saw cutting shall be incidental. <br />Ton <br />Special Specifications Job #4582 Page 7 <br />