02/19/2010 16:26 FAX 541 682 5366 CITY EUGENE PW ENG 4 WILDISH CONST IM 0041010AD <br />00745.48 .Hauling, Depositing and Placing <br />(c) Placing (pace 137) <br />(ADD) The Shoulder may be placed in a single 3 inch lift. <br />108-2.3 BARE COPPER WIRE (COUNTERPOISE OR GROUND) AND G=ROUND RODS. (pg 170) <br />(CHANGE) Second paragraph, from "Ground rods shall be copper" to "Ground rods shall be copper clad <br />or tin plated copper." <br />1.08-3.3 BARE COUNTERPOISE 'M'IRE INSTALLATION FOR LIGHTNING PROTECTION <br />AND GROUNDING (page 172) <br />(ADD) Counterpoise is not required for fixtures outside of paved areas. <br />108-4.1 METHOD OF MEASUREMENT (page 174) <br />(ADD) To end of the paragraph, "The measurement of cable required for slack shall not exceed 1 <br />foot above the proposed grade." <br />108-5.1 BASIS OF PAYMENT (page 174) <br />(ADD) The Contractor shall work with the Airport electrician to determine the necessary temporary <br />electrical jumpers required to maintain the parallel taxiway circuit. The actual wort: necessary to make the <br />jumpers and other temporary work will be paid as force account work, and shall not include planning or <br />other investigative work necessary to schedule other contract work. The bid item "Temporary Electrical - <br />Force Account - FRCACCT" is included in the bid schedule and has been assigned a value of $5,000. The <br />actual arnount paid will be based on actual work performed as a percentage of the $5.000. <br />115-5.2 BASIS OF PAYMENT (page 187) <br />(ADD) Adjustment of existing 1.,-868 centerline and touchdown cans requires the removal of the <br />existing flange ring, and installation of a new flange ring. <br />(ADD) Payment for "Replace Electrical Vault (.1B-A) shall include the work necessary to pull all <br />wiring back to other_junction boxes as necessary, and to make any temporary connections needed to <br />complete the work. <br />RUNWAY WEATHER INFORMATION SYSTEM (page 190) <br />(DELETE) All references to a .Pan-Tilt-Zoom (PTZ.) camera. A PTZ camera is not required for this <br />prgj ect. <br />(ADD) EW B Standard Drawings (5 Pages) <br />CHANGES TO PLAN SHEETS: <br />Sheet D-1 <br />(CHANGE) Shoulder paving may be either P-403 or 00745 material. <br />Addendum ':2 - Job 94625 Page 3 <br />