Page 2
<br />Run Datq: 12/08/2009 09:55:36
<br />City of Eugene
<br />Contract
<br />Preliminary Progress Payment
<br />Payment No : 007
<br />Contractor: KNIFE RIVER
<br />Original Contract: $2,034,034.43
<br />Job 93-004275
<br />Current Amount: $2,034,034.43
<br />Contract No: 2009-00018
<br />Contract Award Date: 05/01/2009
<br />PO 2009100358
<br />Completion Date: 10/01/2009
<br />Assessable: Yes
<br />Current Contract Estimated Payment
<br />Cumulative
<br />Totals
<br />Complete
<br />Line Description Last Chng Ord
<br />Unit Price
<br />unit measure
<br />Quantity Amount Quantity
<br />Amount
<br />Quantit
<br />Amount
<br />ELMIRA-HWY 99 TO BERTELSEN, PAV, C/W, ILLUM & STN
<br />General
<br />0000 Liquidated Damages
<br />($1,000.00)
<br />DAY
<br />0.000 $0.00 0.000
<br />$0.00
<br />0.000
<br />$0.00
<br />0.00
<br />0010 MOBILIZATION
<br />$45,493.18
<br />LUMPSUM
<br />1.000 $45,493.18 0.000
<br />$0.00
<br />1.000
<br />$45,493.18
<br />100.00
<br />0020 TEMP. WORK ZONE TRAFFIC CONTRO
<br />$7,500.00
<br />LUMPSUM
<br />1.000 $7,500.00 0.000
<br />$0.00
<br />0.950
<br />$7,125.00
<br />95.00
<br />0030
<br />EROSION CONTROL
<br />$3,000.00
<br />LUMPSUM
<br />1.000
<br />$3,000.00
<br />0.000
<br />$0.00
<br />0.950
<br />$2,850.00
<br />95.00
<br />0040
<br />CLEARING AND GRUBBING
<br />$15,000.00
<br />LUMPSUM
<br />1.000
<br />$15,000.00
<br />0.000
<br />$0.00
<br />1.000
<br />$15,000.00
<br />100.00
<br />0050
<br />TREE PROTECTION
<br />$2,500.00
<br />LUMPSUM
<br />1.000
<br />$2,500.00
<br />0.000
<br />$0.00
<br />1.000
<br />$2,500.00
<br />100.00
<br />0060
<br />FLAGGERS
<br />$46.00
<br />HOUR
<br />2,700.000
<br />$124,200.00
<br />11.000
<br />$506.00
<br />1,922.000
<br />$88,412.00
<br />71.00
<br />0070
<br />TREE REMOVAL, 5" TO 24"
<br />$600.00
<br />EACH
<br />10.000
<br />$6,000.00
<br />0.000
<br />$0.00
<br />7.000
<br />$4,200.00
<br />70.00
<br />0080
<br />TREE REMOVAL, 25" TO 36"
<br />$700.00
<br />EACH
<br />13.000
<br />$9,100.00
<br />0.000
<br />$0.00
<br />14.000
<br />$9,800.00
<br />108.Q0
<br />0090
<br />TREE REMOVAL, OVER 37"
<br />$800.00
<br />EACH
<br />7,000
<br />$5,600.00
<br />0.000
<br />$0.00
<br />7.000
<br />$5,600.00
<br />100.00
<br />0100
<br />TREE REMOVAL DURING EXCAVATION
<br />$800.00
<br />EACH
<br />10.000
<br />$8,000.00
<br />0.000
<br />$0.00
<br />0.000
<br />$0.00
<br />0.00
<br />0110
<br />REMOVAL OF STRUCTURES AND OBST
<br />$27,560.00
<br />LUMPSUM
<br />1.000
<br />$27,560.00
<br />0.000
<br />$0.00
<br />1.000
<br />$27,560.00
<br />100.00
<br />0120
<br />GENERAL EXCAVATION
<br />$9.00
<br />CUYD
<br />18,894.000
<br />$170,046.00
<br />0.000
<br />$0.00
<br />18,894.000
<br />$170,046.00
<br />100.00
<br />0130
<br />ROOT ZONE EXCAVATION
<br />$40.00
<br />FOOT
<br />250.000
<br />$10,000.00
<br />0.000
<br />$0.00
<br />0.000
<br />$0.00
<br />0.00
<br />0140
<br />6" SUBGRADE STABILIZATION EXCA
<br />$9.50
<br />CUYD
<br />3,304.000
<br />$31,388.00
<br />0.000
<br />$0.00
<br />2,773.000
<br />$26,343.50
<br />84.00
<br />0150
<br />6" SUBGRADE STABILIZATION AGGR
<br />$3.00
<br />SQYD
<br />19,823.000
<br />$59,469.00
<br />0.000
<br />$0.00
<br />14,536.000
<br />$43,608.00
<br />73.00
<br />0160
<br />AGGREGATE BASE, 6 IN. THICK
<br />$4.00
<br />SQYD
<br />19,823.000
<br />$79,292.00
<br />0.000
<br />$0.00
<br />19,823.000
<br />$79,292.00
<br />100.00
<br />0170
<br />RE-USE EXISTING AGGREGATE BASE
<br />$1.00
<br />CUYD
<br />4,000.000
<br />$4,000.00
<br />0.000
<br />$0.00
<br />448.500
<br />$448.50
<br />11.00
<br />0180
<br />SUBGRADE GEOTEXTILE
<br />$1.00
<br />SQYD
<br />19,823.000
<br />$19,823.00
<br />0.000
<br />$0.00
<br />16,143.500
<br />$16,143.50
<br />81.00
<br />0190
<br />6 INCH WW PIPE, C900
<br />$27.00
<br />FOOT
<br />500.000
<br />$13,500.00
<br />0.000
<br />$0.00
<br />0.000
<br />$0.00
<br />0 00
<br />0200
<br />6 INCH WW PIPE, PVC
<br />$27.00
<br />FOOT
<br />500.000
<br />$13,500 00
<br />0.000
<br />$0.00
<br />449.800
<br />$12,144.60
<br />90.00
<br />0210
<br />4 INCH ROOF DRAIN PIPE
<br />$25.00
<br />FOOT
<br />350.000
<br />$8,750.00
<br />0.000
<br />$0.00
<br />117.500
<br />$2,937.50
<br />34.00
<br />
|