Run. Date:, 10/06/2009 09:51:37 Page 2
<br /> City of Eugene
<br /> Contract Preliminary Progress Payment
<br /> Payment No 005
<br /> Contractor: WILDISH CONSTRUCTION Original Contract: $970,348.00
<br /> Job 93-004590 Current Amount: $970,348.00
<br /> Contract No: 2009-00017
<br /> Contract Award Date: 04/10/2009
<br /> PO 2009100341 Completion Date: 09/19/2009
<br /> Assessable: 'No
<br /> Current Contract Estimated Payment Cumulative Totals ~ Complete
<br /> Line Description Last Chng Ord Unit Price Unit Measure Quantity Amount Quantity Amount Quantity Amount
<br /> AIRPORT TERMINAL RAMP RECONSTRUCTION SECTION 2
<br /> General
<br /> 0000 Liquidated Damages ($1,000.00) DAY 0.000 $0.00 0.000 $0.00 O.OOD $0.00 0.00
<br /> 0010 MOBILIZATION $97,000.00 LUMPSUM 1.000 $97,000.00 0.000 $0.00 1.000 $97,000.00.. 100.00
<br /> 0020 EROSION CONTROL $2,000.00 LUMPSUM 1.000 $2,000.00 0.050 $100.00 1 000 $2,000 00 100 00
<br /> 0030 AIRPORT SAFETY AND SECURITY $51,000.00 LUMPSUM 1.000 $51,000.00 0.050 $2,550.00 1.000 $51,000.00 100.00
<br /> 0040 AIRPORT BARRICADES $400.00 EACH 12.000 $4,800.00 0.000 $0.00 12.000 $4,800.00 100.00
<br /> 0050 CONCRETE DEMO AND REMOVAL $14.00 SQYD 7,247.000 $101,458.00 0.000 $0.00 7,247.OD0 $101,458 00 M 1D0 00
<br /> 0060 HMAC COLD PLANING $5.00 SQYD 860.000 $4,30D.00 0.000 $0.00 877.000 $4,385.00 102.00
<br /> 0070 ECONOCRETE $100.00 CUYD 20.000 $2,000.00 0.000 $0.00 20.500 $2,050.00 / 102.00
<br /> 0080 PCC PAVEMENT $80.00 SQYD 7,145.000 $571,60D.00 947.000 $75,76D.00 7,145 000 $571,600 00 M 100 00
<br /> 0090 HMAC $95.00 TON 600.000 $57,000.00 35.000 $3,325.00 845.420 $80,314.90_ ~ 141.00
<br /> 0100 JOINT SEAL $8.00 FT 8,680.000 $69,440.00 0.000 $0.00 8,689.000 $69,512.00 ~ 100.00
<br />
<br /> 0110 OBLITERATE MARKINGS $8.00 SQFT 300.000 $2,400.00 0.000 $0.00 304 800 $2;438 40 F 102 00
<br />
<br /> 0120 MANHOLE ON EXISTING PIPE $3,100.00 EACH 1.000 $3,100.00 0.000 $0.00 1.000 $3,100.00 100.00
<br />
<br /> 0130 6" TEMPORARY TAPE $2.50 FT 500.000 $1,250.00 0.000 $0.00 737.000 $1,842.50 147.00
<br />
<br /> 0140 DETACH/REATTACH JET BRIDGE STA $1,500.00 EACH 2.000 $3,000.00 0.000 $0.00 2.000 $3,000.00 100 00
<br /> $970,348.00 $81,735.00 $994,500.80