Mitigate Open Waterway R/VU 34L <br /> 3/24/2009 <br /> Estimate GJN 4635 <br /> Push fill into adjacent quarry pits <br /> Unit <br /> Unit Qty Cost Total <br /> mob-10% Is 1 $5,778 $5,778 <br /> <br /> .Safety/Security Is 1 $2,000 $2,000 <br /> Erosion Control Is 1 $2,000 $2,000 <br /> Caterpillar D9 Dozer hr 120 $400 $48,000 <br /> Operator hr 120 $65 $7,800 <br /> $65,578 <br /> contingency 10% 6,557.78 <br /> testing $500 <br /> engineering 15% 9,836.67 <br /> consultant 18,000.00 <br /> TOTAL: $100,472 <br /> Assumptions <br /> 21,000 CY of fill staged <br /> Dozer pushes fill into nearest pond edge <br /> Not purchasing extra fill material <br /> End result is skinnier ponds east to west <br /> No wetland mitigation required <br /> Minimal inpsection needed <br /> Minimal material testing needed . <br /> <br /> Job done in twelve 10 hour days <br /> <br />