. t, <br /> INTERGOVERNMENTAL AGREEMENT <br /> AMENDMENT NO. 1 <br /> PW#: 03102003 <br /> City of Eugene Contract 2004-00219 <br /> AGREEMENT: Judkins Point Interchange DATE: July 7, 2005 <br /> (Glenwood} Improvements -Project 0870-5 <br /> AGENCY: City of Eugene CONTRACT DATE: 11/17/03 <br /> ADDRESS: 858 Pearl Street, Suite 300 PREVIOUS AMEND DATE: None <br /> Eugene, OR 97401 <br /> WHEREAS, per Board Order 02-8-13-3, Lane County granted up to $200,000 under its Community <br /> ~ Development program to the City of Eugene to assist with the Judkins Point North Interchange Glenwood <br /> Boulevard improvements; and <br /> i <br /> WHEREAS, per Board Order 04-6-23-9, the Board of County Commissioners amended the Public Works <br /> Five-Year Capital Improvement Program (CIP) for FY 04105 - FY 08109 granting an additional $220,000 <br /> under,Payments to Other Government Agencies for the Judkins Point South interchange improvements. <br /> NOW THEREFORE, the agreement is amended as outlined below. <br /> ALL OTHER TERMS AND .CONDITIONS SHALL REMAIN IN FULL FORCE AND EFFECT. <br /> RECITALS, No. 5, page 1, which now reads: <br /> 5. Per Board Order No. 02-8-13-3, COUNTY has granted up to $200,00 under COUNTY's CD program <br /> to assist with the Judkins Point Interchange Glenwood Boulevard improvements as described beVow, <br /> hereinafter referred to as PROJECT; and <br /> Shall be amended to read: <br /> 5. Per Board Order No. 02-8-13-3, COUNTY has granted up to $200,000 under COUNTY's CD program <br /> to assist with the Judkins Point North Interchange Glenwood Boulevard improvements as described <br /> below. Per Board Order No. 04-6-23-9, COUNTY has granted up to $220,000 under Payments to Other <br /> Government Agencies in the FY 05-09 Capital Improvement Program for the Judkins Point South <br /> Interchange improvements as described below. Both portions of the project are hereinafter referred to as <br /> PROJECT; and <br /> RECITALS, No. 6, page 1, which now reads: <br /> 6. Glenwood Boulevard is an approximately 22-foot wide asphalt roadway with approximately 6-foot wide <br /> gravel shoulders and open ditches on both sides of the existing roadway. The proposed project will <br /> widen the roadway to a 36-foot wide paved surface with 4-foot gravel shoulders and open ditches on both <br /> sides. Existing guardrail sections at.the bridge ends and along the north side of the northbound freeway <br /> off-ramp and north side of 22"d Avenue will be reconstructed. <br /> ' Shall be amended to read: <br /> 6. Glenwood Boulevard is an approximately 22-foot wide asphalt roadway with approximately 6-foot wide <br /> gravel shoulders and open ditches on both sides of the existing roadway. The proposed Judkins Point <br /> North project will widen the roadway to a varying width up to a 48-foot wide paved surface with 4-foot <br /> gravel shoulders and open ditches on both sides. The existing on/off ramp will be widened and a left turn <br /> Exhibit B <br /> <br /> I ~ PaQe 5 of 7 <br /> <br />