Terminal Ramp Section II <br />8/28/2008 <br />Estimate Pre GJN <br />13.5" PCC on existing CTB <br />66000 sf <br /> Unit <br /> Unit Qty Cost Total <br />mob-10% Is 1 $ 117,704 $ 117,704 <br />Safety/Security Is 1 $ 100,000 $ 100,000 <br />Erosion Control Is 1 $ .4,000 $ 4,000 <br />Concrete Demo sy 7333 $ 20 $ 146,667 <br />HMAC Cold Planing sy 1000 $ 10 $ 10,000 <br />Econocrete cy 200 $ 100 $ 20,000 <br />PCC Pavement sy 7333 $ 80 $ 586,667 <br />Joint Seal ft 8000 $ 10 $ 80,000 <br />HMA to 1200 $ 85 $ 102,000 <br />Striping sf 5000 $ 2 $ 10,000 <br />Modify Driveway sy 225 $ 100 $ 22,500 <br />Temporary Stripe ft 1000 $ 4 $ 4,000 <br />Detach/Attach Jet Bridge ea 2 $ 5,000 $ 10,000 <br />Manhole on Existing ea 1 $ 8,000 $ 8,000 <br />Adjust Electrical ea 2 $ 1,500 $ 3,000 <br />Adjust Storm ea 2 $ 1,500 $ 3,000 <br /> $ 1,227,537 <br />contingency 10% 122,753.70 <br />testing $ 15,000 <br />engineering 16% 196,405.93 <br />airport admin 40,000.00 <br /> TOTAL: $ 1,601,697 <br />