Run Date: 08/06/2008 08:18:53 Page 5
<br /> City of Eugene
<br /> Contract Preliminary Progress payment
<br /> Payment No OD3
<br />Contractor: WILDISH CONSTRUCTION Original Contract: $926,017.00 °
<br /> Job #: 93-004433 Current Amount: $989,839.69
<br />Contract No: 2008-00022 Contract Award Date: 05/02/2 008
<br /> PO #: 2008100425 Completion Date: 07/20/2 008
<br />Assessable: No
<br /> Current Contract Estimated Payment Cumulative Totals 8 Complete
<br />Line Description Last Chng Ord Unit Price Unit Measure Quantity Amount Quantity Amount Quantity Amount
<br />0400 MULCH $60.00 CUYD 1.000 $60.00 1.500 $90.00 1.500 $90.00 150.00
<br />0410 TOPSOIL $50.00 CDYD 11.000 $550.00 21.700 $1,085.00 21.700 $1,085.00 197.00
<br />0420 LAWN SEEDING $2.00 SQFT 450.000 $900.00 0.000 $0.00 0.000 $0.00 0.00
<br />0430 3/4" RIVER ROCK $80.00 TON 2.500 $200.00 1.800 $144.00 1.600 $149.00 72.00
<br />y~~
<br />PPP Barger DR from Hwy 99 to Altimont
<br />~\ $405,648.43 .,('V`~~
<br />`~ $33,595.28 $432,505.08
<br />General ~
<br />~^~
<br />0000 Liquidated Damages-Barger/Hwy ($310.00) DAY 0.000 $0.00 0.000 $0.00 0.00
<br />0010 MOBILIZATION^ $20,000.00 LUMPSUM 1.000 $20,000.00 0.000 $0.00 1.000 $20,000.00 100.00
<br />0020 TEMP. WORK ZONE TRAFFIC CONTRO $7,000 00 LUMPSUM 1 000 $7,000 00 0 500 $3,500.00 1.000 $7,000.00 100.00
<br />0030 TEMPORARY STRIPING $2,000.00 LUMPSUM 1.000 $2,000.00 0.000 $0.00 1.000 $2,000.00 100.00
<br />0040 FLAGGERS $37.00 HOUR 350.000 $12,950.00 0.000 $0.00 315.500 $11,673.50 90.00
<br />0050 EROSION CONTROL $700 00 LUMPSUM 1 000 $700 00 0 500 $350.00 1.000 $700.00 100.00
<br />0060 CITY PROVIDED SPEC INFO SIGNS $150.00 EACH 4.000 $600.00 0.000 $0.00 4.000 $600.00 100.00
<br />0070 SURFACING STABILIZATION $90.00 CUYD 200.000 $16,000.00 0.000 $0.00 632.700 $56,943.00 316.00
<br />0080 ADJUSTING BOXES $150 00 EACH 4 000 $600 00 D 000 $0.00 1.000 $150.00 25.00
<br />0090 MINOR ADJUSTMENT OF MANHOLES $1,200.00 EACH 6.000 $7,200.00 0.000 $0.00 5.000 $6,000.00 83.00
<br />0100 MH REM/REPL FRAME/COVER-WW $300.00 EACH 3.000 $900.00 0.000 $0.00 2..000 $600.00 67.00
<br />0110 MH REM/REPL FRAME/COVER-ST $300 00 EACH 3 000 $900 00 0 000 $0.00 3.000 $900.00 100.00
<br />Oi20 PAVEMENT REMOVAL $20.00 SQFT 18.000 $360.00 0.000 $0.00 15.000 $300.00 83.00
<br />0130 COLD PLANE PVMT REMOVAL, 2.5" $0.15 SQFT 86,400.000 $12,960.00 0.000 $0.00 87,908,500 $13,186.28 102.00
<br />0140 LEVEL 3, 1/2" DENSE, HMAC $58 00 TON 1,400 000 $81,200 00 29 630 $1,718.54 1,291.350 $74,898.30 92.00
<br />
<br />0141 1/2" LEV 2 HMAC-JUNE PRICE ADJ 001 $4.53 TON 1,261.720 $5,715.59 1,261.720 $5,715.59 1,261.720 $5,715.59 ~ 100.00
<br />0142 SURFACE STABILIZATION HMAC-1/2 002 $77.24 TON 430.270 $33,234.05 430.270 $33,234.05 430.270 $33,234.05 100.00
<br />
|