(10) linear feet of curb and gutter shall be removed and replaced. An alternative to this <br /> requirement shall be removing and replacing three (3) linear feet of curb and gutter with the <br /> new curb and gutter tied into the existing curb by inserting 6"X #4 rebar dowels into drilled <br /> one-half inch diameter by three (3) inch deep holes in the adjoining existing curbs and <br /> gutters, one dowel in the curb and two dowels in the gutter at each end of the replaced <br /> section. <br /> When the gutter bar portion of the curb and gutter is removed along an asphalt street, at least <br /> 24 inches of asphalt concrete shall be removed to allow sufficient room for placement of the <br /> forms for the new face of gutter and proper compaction of asphalt restoration. An alternate <br /> to removal of adjacent asphalt shall be to saw cut the asphalt at the face of the gutter bar, <br /> using the edge of asphalt as the form for concrete replacement. When the curb is removed <br /> but the gutter bar is left in place, epoxy shall be used on the back of the gutter to bond the <br /> existing P.C.C. to the new P.C.C. being placed (i.e. at driveways, handicapped access ramps, <br /> etc.). <br /> 14. Any traffic control devices (signing, striping, pavement markers, traffic signal loops, etc.) <br /> damaged or removed during the work allowed by the permit shall be replaced by the <br /> permittee. <br /> 15. Bicycle/wheelchair ramps and bypasses shall be constructed or upgraded whenever a curb, <br /> driveway approach, or sidewalk is constructed, improved or replaced at any point in a block <br /> which gives reasonable access to a crosswalk and where no ramp currently exists. (ORS <br /> 447.310) i <br /> 16. The permittee shall notify the Inspector at least one full business day in advance of the time <br /> any permanent surface restoration is to be made by the permittee's own staff or that of <br /> contractors working for the permittee. <br /> 17. The elevation of finish grade for underground vaults shall be at least 18" below the finish <br /> grade of the surface A.C. or P.C.C. <br /> 18. Above ground facilities shall not be placed in a manner which would cause a vision <br /> obstruction as defined by Eugene Code Section 6.010 (j). <br /> 19. When wastewater lateral markers in new developments (typically 2"x 4" wood posts) are <br /> damaged, they shall be replaced by the permittee or the permittee's contractor. This <br /> replacement shall require excavation to uncover the wastewater lateral and ensure the correct <br /> location for the replacement marker. <br /> 20. Catch basins or storm inlets abutting the work area shall be inspected by the permittee or <br /> their contractor at the conclusion of work and cleaned of construction related debris as <br /> necessary. <br /> <br /> Utility & R/W Permit Policy <br /> Exhibit A - 26 r:\adminord\rules\OOrowrlexa.wpd(09/13/00) <br /> <br />