Public Works <br />Engineering <br />City of Eugene <br />244 East Broadway <br />Eugene, Oregon 97401 <br />(541) 682-5560 <br />(541) 682-8410'FAX <br />..Memorandum <br />Date:. July 22, 2008 <br />To: File <br />From: Matt Rodrigues, Project Manager <br />Subject: GJN 4483.. PPP Barger Dr.-Additional budget authorization due to increased Surface <br />Stabilization <br />All, <br />Once milling was completed and a few spot surface stabilization repairs had been <br />performed on Barger Dr. we found that an approximately 1200-foot section of <br />pavement 7' to 10' wide adjacent to the north curbline was unstableand failing as <br />work progressed. Investigation showed that this section of the street was constructed <br />as part of a widening project as was approximately 3 to 5 inches of deteriorated <br />pavement on subgrade. Passage of a 3/4 ton truck showed substantial deflection on this <br />pavement. It was decided after examining the pavement along this line to expand the <br />.quantity to include the length and width of the widened section as discussed above. <br />This led to approximately $64k in additional contract work and increased inspection <br />costs on the project. This budget request is to increase the project budget to cover this <br />work and allow. us to pay the Contractor for this work in the coming pay period. <br />~~~ <br />