Run ~ate: 08/06/2008 16:18:19
<br />Contractor: WILDISH CONSTRUCTION
<br />Job #: 93-004417
<br />Contract No: 2008-00019
<br />PO #: 2008100380
<br />Assessable: No
<br />City of Eugene
<br />Contract Preliminary Progress Payment
<br />Payment No : 003
<br />Original Contract: $977,090.7D
<br />Current Amount: $977,090.70
<br />Contract Award Date: 03/27/2008
<br />Completion Date: 09/20/2008
<br />Page 2
<br /> Current Contract Estimated Payment Cumulative Totals ~ Complete
<br />Line Description Last Chng Ord Unit Price Unit Measure Quantity Amount Quantit Amount QuantitY Amount
<br />
<br />AIRPO RT-TERMINAL RAMP RfiAAB
<br />Base Bid
<br />0000 Liquidated Damages ($1,OOO.DO) DAY 0.000 $0.00 0.000 $0.00 0.000 $0.00 0.00
<br />0010 MOBILIZATION $94,000.00 LUMPSUM 1.000 $94,000.00 0.000 $0.00 1.000 $94,000.00 100.00
<br />0020 EROSI~N CONTROL $3,500.00 LUMPSUM 1.000 $3,500.00 0.000 $0.00 0.800 $2,800.00 80.00
<br />
<br />OD30 AIRPORT SAFSTY AND SECURITY $83,000.00 LUMPSUM 1.000 $83,000.00 0.280 $23,240.00 0.780 $64,740.00 78.00
<br />0040 CONCRETE DEMO AND REMOVAL $9.D0 SQYD 7,341.000 $66,069.00 0.000 $0.00 3,634.000 $32,706.00 50.00
<br />OD50 HMAC COLD PLANING $8.00 SQYD 1,050.000 $8,400.00 0.000 $0.00 346.000 $2,768.00 33.00
<br />
<br />0060 ECONOCRETE $100.00 CUYD 50.000 $5,000.00 0.000 $0.00 0.000 $0.00 0.00
<br />0070 PCC PAVEMENT $76.50 SQYD 7,172.000 $548,658.00 2,794.400 $213,771.60 3,430.400 $262,425.60 M 48.00
<br />0080 ADNST JUNCTI4N BOX $500.00 EACH 1.000 $500.00 0.000 $0.00 1.000 $500.00 1D0.00
<br />
<br />0090 HMAC $76.00 TON 600.000 $45,600.00 59.950 $4,556.20 328.710 $24,981.96 55.00
<br />0100 PREFORMED JOINT SEAL $B.OD FT 8,000.000 $64,000.00 2,964.000 $23,712.00 2,964.000 $23,712.00 37.00
<br />0110 OBLITERATE EXISTING MARKING $2.25 SQFT 3,500.000 $7,875.00 0.000 $0.00 2,248.000 $5,058.00 64.00
<br />
<br />0120 PAVEMENT MARKING $1.65 SQFT 13,000.000 $21,450.00 118.000 $194.70 1,504.500 $2,482.43 12.00
<br />Alt-3 Concrete Driveway Replacement
<br />0160 CONCRETE DRIVEWAY REPLACEMENT $68.00 SQYD 225.000 $15,300.00 0.000 $0.00 242.500 $16,490.00 108.00
<br />Alt-1 High Frequency Demolition
<br />0170 MOBILIZATION-RUBBLIZING EQUZPM $4,300.00 EACH 2.000 $8,600.00 0.000 $0.00 1.000 $4,300.00 50.00
<br />0180 PAVEMENT RUBBLIZING $0.70 SQYD 7,341.000 $5,138.70 0.000 $0.00 3,601.000 $2,520.70 49.00
<br /> $977,090.70 $265,474.50 $539,484.69