a <br /> <br />Change Order <br />CITY OF EUGENE <br />DEPARTMENT OF PUBLIC WORKS <br />ENGINEERING DIVISION <br />Job # <br />Contract # 2004-20 <br />Change Order # 4 <br />Date: 2/18/2005 <br />CAMS Date: <br />CONTRACTOR Wildish Construction Company <br />(ADDRESS) P O Box 7428 <br />Eugene, OR 97401-0428 <br />PROJECT: Paving curbs, gutters, sidewalks, median, street lights, traffic signal. <br />street trees wastewater, and stone water drelnage on Garden Way from <br />Sisters View Ave. to Martin Luther King Jr. Bld. north side of Martin Luther <br />King Jr. Blvd. from Marche Chase Drive to I-5 <br />You are directed to make the following changes in this contract: <br />contract <br />Reviewed b : Date: <br />Inspector. John Bonham <br />Constr. Mgr. Pai a Dickinson <br />Proj. AAgr. Steve Gallu C_ <br />Principal Eng. Paul Klope <br />3502 <br />Item <br />No. <br />1310 re it Vandalism da a to teeters and landsca in items <br /> <br /> <br /> <br />1 ADA ram than eat Westward Hoe Ave <br /> <br />1 Electrical work items <br /> <br />1 Provi a Credit to c' for usi existin 1-1/2" conduit <br /> <br />1 re additional irti ation sleeves at 348 South Garden Wa <br /> <br /> <br /> <br />This Changes the bid items as follows: <br />r~~trprr <br />Contract <br />item <br />No. Item Time <br />Chan a 4uantity <br />Units Unit <br />Cost <br />Amount <br />+/- Amended <br />Chan a Net <br />Chan e <br />1310 landsWping Vandalism Ori anal 0.00 0.00 .00 ;0.00 <br /> Revised 0.00 .00 .00 <br /> Amended 1.00 LS 1587.00 1587.00 1587.00 <br /> Inal 0.00 .00 .00 #0.00 <br /> Revised 0.00 .00 0.00 <br /> Amended 0.00 0.00 .00 ;0.00 <br />1380 sidewalk and ada ramp at Westward Hoe Ave final 0.00 .00 0.00 ;0.00 <br /> Revised 0.00 0.00 .00 <br /> Amended 1.00 lS 1667.64 1667.64 1667.64 <br />1340 EIeWlcal work items 0 final 0.00 0.00 0.00 ;0.00 <br /> Revised 0.00 .00 .00 <br /> Amended 1.00 LS 1449.36 1449.36 1449.36 <br />1350 Credit to dty, Use ex 1-U2" conduit Ori anal 0.00 0.00 0.00 ;0.00 <br /> Revised 0.00 0.00 .00 <br /> Amended 1.00 LS 2400.00 2400.00 2400.00 <br />1360 Bore 3 Irrigation cleaves inai 0.00 .00 .00 ;0.00 <br /> Revised 0.00 .00 .00 <br /> Arrknded 1.00 LS 1611.00 1611.00 1611.00 <br />The original contract work days are o.o da <br />The contract time change this C.O o.o da <br />The contract time change by previous C.O's o.o da <br />The new contract work da are o.o da <br />The original contract sum was ,,,,,,,,,,,,,,,,,,,_. <br />Net Change by previous change order ,,,,-.,,,,-„-,,,,,, <br />~ change due to amendment by previous change order <br />The contract sum prior to this change order was <br />This change order will change contract sum by this amount ,,,,,,,,,,,,,,_,.,..,,,,,,,,,,,,_,_____„_,,,,,,,_.,,,,,,,,,,__,_„_.._........_....-_.... <br />The new wntrail net change sum <br />...-..._...._.-...._._......____-__..._._....___~...-...w.....____.___-... <br />The new contrail amendment sum <br />....................__~....__._..........m..._...............__......-.......-._.-......._.......-_......_.. _._.w......._ <br />The new contract sum including this change order will be ,_„_,,._,,,,,,,~,,,,__,,,,,,_„_,,,,,_,_,_,,,,__..,.._ <br />n e of on Ig'nal contrail <br />HA ~ G DUE TO AM NDMENTS <br />Approval by: <br />Ci E ineer M-~QiL U~ <br />ty ng <br />~I ~i~ <br />Dat <br />~J CONTRACTOR ^ OFFICE FILE <br />079.450.75 <br />i51,3aa.oo~ <br />531,077.33 <br />$2,109,180.08 <br />$3,915.00 <br />(51.348.00) <br />534,992.33 <br />52.113,09b.08 <br />1.s2~ <br />1.68% <br />Third Party <br />Date <br />Q\FORMS\PROJECTCONSTIREVISED CHANGE ORDER.XLS <br />