URS Greiner Woodward Clyde <br /> <br /> Project Team <br /> We propose to use the following URS staff to conduct this work: <br /> • Project Manager John Holroyd, P.E. <br /> • Modeling Binhong Wu, Mike Fowler <br /> • Report and FEMA application Binhong Wu, Mike Fowler <br /> • Peer Review Don Glondys (URS Chicago office FEMA expert) <br /> Schedule <br /> The project schedule is presented in Figure 1 and Table 3. <br /> Table 3: Estimated Project Schedule <br /> TASK ESTIMATED TIME TO ESTIMATED DATE TO <br /> COMPLETE COMPLETE** <br /> 1. Data Collection 1-2 WEEKS* 2/28/2000- 3/6/2000* <br /> 2. Hydrologic Analysis 2-3 WEEKS 3/13/2000- 3/27/2000 <br /> 3. Hydraulic Analysis 10 WEEKS 5/22/2000 - 6/5/2000 <br /> 4. Floodplain and Floodway Identification 2-3 WEEKS 6/5/2000 - 6/26/2000 <br /> S.Complete FEMA Application and 4-5 WEEKS* 7/3/2000 -7/31/2000* <br /> Documentation <br /> 6. Review by City Staff 2-4 WEEKS 7/17/2000 - 8/28/2000 <br /> 7. FEMA Approval Process 12-24 WEEKS 10/9/2000 - 2/19/2001 <br /> TOTALS 33 -52 WEEKS or 8 -13 <br /> MONTHS <br /> * This is based on the assumption that the City and Army Corps of Engineers would provide all necessary <br /> information in time. <br /> Assuming the project starts on 2/21/2000. <br /> Sincerely, <br /> URS CORPO ION <br /> ictor Vie s, P.E. J n Holroyd, P.E. <br /> Vice President Project Manager <br /> Authorization to Proceed: Si natu~~ti~ v ~~f <br /> g <br /> Date: <br /> \\Pur2\PROD-WC1945(M2na\TASK030(hAMAZOt~I\FEMA\fcma.doc 4:08 PM 02/25HK) Page 7 <br /> <br />