CITY OFEUGENE -LOWER AMAZON FEMA STUDY <br /> <br /> URS Corporation Project #52-945042ND.07 <br /> Eugene Design Task <br /> roject Manager: Binhong Wu <br /> Progress Report 16 <br /> Period beginning June 2, 2001and ending July 6, 2001 <br /> 'I. Budget Status Total Previous Expenditures: $52,960 <br /> Total Current Invoice: $4,568 <br /> Total Billed: $57,528 <br /> Contract Amount: $59,540 <br /> It. Project Work • Held conference calls with the City to determine whether floodway analysis is <br /> Completed needed for the Lower Amazon Creek and what extent of the Greenhill Tributary <br /> should be included in the LOMR. <br /> • Held a conference call with Max Yuan from FEMA headquarters and Sheila <br /> Norlin from Michael Baker to discuss our proposed approach for the <br /> hydrologic/hydraulic analyses. <br /> • Worked on finalizing the contract addendum. <br /> III. Work to be • Work with Therese and Steve to finalize the contract addendum and budget <br /> Completed during information. <br /> the Next Period • Coordinate with Doug Putman from the Corps and Bud DeSantis from the City on <br /> the 1135 project levee certification. <br /> • Meet with Larry Basich from FEMA Region X office to discuss the next steps for <br /> the LOMR. <br /> • Prepare a memorandum to describe our proposed approach and submit to the City <br /> and FEMA for approval. <br /> • Based on the City's decision, prepare and start the hydraulic analysis for the next <br /> phase. <br /> IV. Outstanding The sub-basin delineation maps used to develop the HEC-1 model for the <br /> Requests for Amazon Basin by OTAK in 1990. <br /> Information <br /> \\PpR2\PROIECTS\945042ND\AMAZONFEMA\PROJECTMANAGEMENT\PR16.DOC 07-20-01 <br /> <br />